Quarterly Activities & Cashflow Reports
Released
Released
Announcement PDF
Parkway Minerals NL
ASX
ACN 147 346 334
Announcement
19 January 2021
ASX:
FSE:
Level 1, 677 Murray Street
West Perth WA 6005
PO Box 174
West Perth WA 6872
Australia
T +61 8 9479 5386
parkwayminerals.com.au
PWN
4IP
DECEMBER 2020 – QUARTERLY REPORT
Highlights
TECHNOLOGY PLATFORM
•
aMES® Technology
o
o
o
Successful commissioning of state-of-the-art aMES® pilot plant.
Completion of the Karinga Lake Potash Project (KLPP) PFS, highlighting
significant performance advantages of the aMES® technology.
The KLPP-PFS and the new aMES® pilot plant are supporting discussions with
prospective clients, to commercialise the process technology platform.
•
iBC® Technology
o Recent testwork on CSG project derived brine, has demonstrated significant
operational, financial and sustainability advantages of the iBC® technology.
•
Other
o
Significant progress in leveraging the technology platform, to support existing
and emerging business development initiatives, including in the development
of several proposals, predominantly for major energy and mining companies.
o
o
Acquired IP portfolio and strengthened collaboration with Victoria University.
Trade mark registration for both aMES® and iBC® awarded by IP Australia.
CORPORATE
•
Ongoing investor engagement through a series of presentations and webinars.
•
Strong balance sheet with $2.62 million in cash and $2.40 million in marketable
securities (34.3 million shares in Davenport Resources, ASX: DAV, plus options).
•
Reported cash balance at end of quarter, excludes grant funds and anticipated R&D
tax incentive rebate of $0.235 million for FY20.
•
Commenced incubation of synergistic new corporate development initiative.
Parkway Minerals NL (ASX: PWN) (“Parkway Minerals” or the “Company”) is pleased to
report its activities for the quarter ending 31 December 2020.
TECHNOLOGY PLATFORM
The Company continues to make strong progress in building and commercialising a worldclass wastewater processing technology portfolio. In addition to the patented iBC® and
aMES® technologies, the Company has recently been offered the rights to certain synergistic
technologies, with high-value industrial applications, including the potential destruction of
problematic environmental contaminants such as hydrocarbon residues and PFAS.
On 18 November 2020, the Company announced the acquisition of several water and
wastewater processing related innovations, as well as certain underlying intellectual property
(IP) in order to consolidate complete ownership of all IP, as part of an expanded
collaboration with Victoria University.
Notwithstanding opportunities to strategically grow the technology portfolio, the Company
remains focused on commercialising the core iBC® and aMES® technologies. The Company
was recently granted the registered trade mark for both these technologies, by IP Australia.
>> Additional details about the recently granted trade marks is described in the
section, Activities Subsequent to Reporting Period.
iBC® Technology
The iBC® technology, provides the opportunity to pre-treat complex brines, particularly from
the coal-seam gas (CSG) industry, in order to enable further downstream processing, to
reduce wastewater volumes and recover valuable chemical products. During the quarter,
ongoing technology optimisation studies identified an additional processing advantage of the
iBC® technology, which had not previously been recognised. As this innovation is believed to
be highly novel, the Company is exploring opportunities for potentially patenting this process,
as it is likely to have broader applications for processing wastewater from the global oil and
gas industry. This anticipated patenting process may allow the company to further expand IP
protection of the technology through a patent “evergreening” process.
Business Development
As outlined in recent updates, the Company is exploring the potential application of the iBC®
technology with a number of major CSG industry participants.
One of the more advanced investigative studies performed during the quarter, involved iBC®
based pre-treatment of a CSG derived wastewater sample supplied by a major CSG project
operator. Preliminary findings indicated, a wastewater volume reduction of greater than 90%
was achievable, with the subsequent integration of the aMES® technology, potentially
providing a highly desirable, zero-liquid discharge (ZLD) solution for the client. Whilst the
annual net benefit1 to the client was initially estimated to be in the order of $4 – 5 million; when
taking actual (realistic) disposal costs into account (as provided by the client) – the recurring
net benefit to the client is expected to be almost an order of magnitude larger, at over $40
million, annually, highlighting the scale of the opportunities being evaluated by the Company.
Discussions are also continuing with other major CSG industry participants, in order to perform
brine characterisation studies, incorporating piloting with the iBC® technology. Internal
technoeconomic evaluations performed by the Company on several Australian projects,
highlight significant opportunities for applying the Company’s suite of technologies, to address
these increasingly pressing challenges.
1 The “annual net benefit” described above is based on internal preliminary technoeconomic assessments (revenues + savings – costs), is indicative only, will change
materially as subsequent evaluations are progressed and should not be relied upon for any purpose. These amounts do not reflect any form of guidance.
December 2020
|
QUARTERLY REPORT
| 2
aMES® Technology
The aMES® technology enables the processing of concentrated feedstocks including brine
solutions, to recover a range of valuable compounds, reagents and fresh water.
Karinga Lakes Potash Project – Pre-Feasibility Study (KLPP-PFS)
On 5 November 2020, the Company announced the completion of the KLPP-PFS, based on
the aMES® technology, with the PFS jointly developed by Parkway Minerals and Worley, under
a Global Strategic Cooperation Agreement announced on 8 May 2020.
The KLPP-PFS enabled the Company to demonstrate the significant advantages of the
aMES® technology, as well as support strategic capability development.
>> Additional information about the Karinga Lakes Potash Project, including the PFS,
is outlined in the Projects section, below.
aMES® Pilot Plant
Initial commissioning of the new, state-of-art aMES® pilot plant commenced in mid-December
2020, and was recently completed, successfully. Additional commissioning related activities
resumed in mid-January 2021, as part of a broader process piloting campaign. The planned
commissioning campaign will incorporate potassium enriched mixed salts from the KLPP.
Subsequent testwork involving the aMES® pilot plant, will also include feedstock from thirdparty projects, providing the Company with an important process demonstration, optimisation
and validation capability, an essential requirement for successful commercialisation of the
aMES® technology.
Business Development
During the quarter, the Company remained focused on achieving the key priorities of the
corporate strategy, including completion of the KLPP-PFS, construction and commissioning
of the new aMES® pilot plant and associated capability development. Towards the end of the
quarter (immediately after completion of the KLPP-PFS), the Company revisited a number of
opportunities, including several significant projects which have previously undergone aMES®
based piloting studies, but could not be advanced at the time. As outlined in the 01 December
2020 presentation (slide 23), the Company was able to perform a range of technoeconomic
studies and finalise a number of proposals, which have been warmly received by the
prospective clients. Whilst the indicative findings of these studies are illustrative only, they
serve to highlight the scale of the opportunities the Company is seeking to address.
Discussions with these parties resumed in early 2021, in an effort to determine a suitable
pathway to further advance collaborative discussions towards commercial arrangements.
Capability Development
Capability Development
The Company continued to make significant progress in building the Brine Processing
Technology Platform (refer Figure 1), including in relation to:
•
Expanding In-House Engineering Capabilities – the Parkway Minerals process
engineering team continues to build significant process simulation and
technoeconomic modelling capabilities, enabling more efficient development,
optimisation and evaluation of a range of process flowsheets incorporating aMES®
December 2020
|
QUARTERLY REPORT
| 3
technology. These practical capabilities provide Parkway Minerals with a strong
foundation from which to develop effective Brine Processing as a Solution™ offerings.
•
Commercialisation & EPC Support – global engineering company, Worley, continues
to assist Parkway Minerals with the commercialisation of the aMES® technology, by
providing strategic and business development support as well as the provision of
engineering, procurement and construction (EPC) related support.
•
Strategic Alignment – collaboration with key partners including ongoing vendor
qualification (OEM’s) and engagement with specialist partners important in the
successful commercialisation of the iBC® and aMES® technologies, is ongoing.
Significant progress has been made in aligning these technologies with high-quality
vendors which would be necessary to deliver a high-quality solution. Several potential
strategic partnership opportunities are currently under active evaluation.
•
Technology Platform – Parkway Minerals has successfully combined a range of key
capabilities, including those outlined above, to strategically develop an innovative brine
processing technology platform (refer Figure 1).
Figure 1: Building a Brine Processing Technology Platform
December 2020
|
QUARTERLY REPORT
| 4
PROJECTS
Karinga Lakes Potash Project (KLPP)
Parkway Minerals currently holds an equity interest in a single mining exploration project, the
Karinga Lakes Potash Project (KLPP). During the quarter no substantive mining exploration
activities occurred in relation to this project.
Overview (KLPP, 15% interest, earning 40%)
The KLPP in the Northern Territory, is a JV between Verdant Minerals and Consolidated
Potash Corporation Pty Ltd (CPC, a wholly owned subsidiary of the Company). CPC acquired
an initial 15% interest in the KLPP by completing a scoping study in February 2019. On 11
May 2020, Parkway Minerals announced the commencement of a pre-feasibility study (PFS)
on the project, based on the strategic application of the aMES® technology.
On 05 November 2020, the Company announced completion of the KLPP-PFS. Based on the
completion of the PFS, and the near-term activities, the Company anticipates satisfying the
earn-in requirements to have acquired a 40% working interest in the project, without making
significant further investment.
Key Findings of the KLPP-PFS
•
The KLPP-PFS confirms the KLPP as a potentially attractive producer of high-quality,
soluble grade, sulphate of potash (SOP) targeting key horticulture markets.
•
Innovative aMES® based flow sheet demonstrates potential (major improvement over
scoping study), even for a relatively small-scale operation targeting annual SOP
production of 40,000 tonnes, over an initial mine life of 20 years.
•
aMES® based development concept demonstrates highly efficient use of water.
•
KEY FINANCIAL METRICS
o
Initial capital cost (CAPEX) of $80.0 million, inclusive of all non-process
infrastructure and indirect costs (which includes a contingency of $6.7 million).
o
Production cost (OPEX) of $293/tonne of SOP, ex-mine gate.
o
Strong cash generation potential, with estimated EBITDA margin of 54.4%,
resulting in annual EBITDA of $18.6 million.
o
Ungeared development of the KLPP would result in:
Project payback in approximately 5.5 years from first SOP production.
Post-Tax NPV8% of $80.15 million with an IRR of 20.4%.
•
Significant additional opportunities to improve the financial performance of the project
were identified, particularly in relation to non-process infrastructure.
•
KLPP-PFS prepared by owners’ team, supported by leading industry consultants, with
Worley as study manager, through existing Global Strategic Cooperation Agreement.
Tenement Rationalisation
As announced previously, the operator of the KLPP, Verdant Minerals is currently undertaking
a tenement rationalisation process focused on holding essentially a similar project area, by
consolidating exploration tenure from 7, to 3 contiguous licences, therefore simplifying
December 2020
|
QUARTERLY REPORT
| 5
dealings with relevant stakeholders as well as potentially reducing holding costs. Parkway
Minerals has been advised by the operator that the Northern Territory Government’s intention
to rely on the expedited procedure for assessing the grant of the new exploration licences has
been objected to by the Central Land Council (CLC) as a result of a Native Title Claim. The
Tribunal dealing with the matter has asked the parties, namely the Northern Territory
Government and the CLC to provide certain supporting information. Discussions between the
respective parties continued during the quarter.
Mineral Resources
The Mineral Resource Estimate underpinning the KLPP-PFS is summarised in Figure 2.
Mineralisation Contained
in Drainable Porosity
Indicated Mineral Resource
contained in Total Porosity
that meets reasonable
prospects of economic
extraction
Production
Potassium Tonnage
Potassium Tonnage
Potassium Tonnage
(kt)
(kt)
(kT)
300
580
430
Sub total
220
430
Totals
520
1000
Lake
Lakes included in the mine plan (x8)
Sub Total
Remaining Lakes (x16)
430
Figure 2: KLPP Mineral Resource Estimate - Resource Utilisation in Mine Plan
The Mineral Resource estimate underpinning the production targets in this announcement
were prepared by a competent person in accordance with the requirements of the JORC Code
2012.
COMPETENT PERSONS STATEMENT
The information in this announcement that relates to Exploration Results and Mineral
Resources for the Karinga Lakes Potash Project is based on, and fairly represents, information
compiled by Mr Ben Jeuken, who is a member of the Australian Institute of Mining and
Metallurgy and a member of the International Association of Hydrogeologists. Mr Jeuken is
employed by Groundwater Science Pty Ltd, an independent consulting company. Mr Jeuken
has sufficient experience, which is relevant to the style of mineralisation and type of deposit
under consideration and to the activity, which they are undertaking to qualify as a Competent
Person as defined in the 2012 Edition of the ‘Australasian Code for Reporting of Exploration
Results, Mineral Resources and Ore Reserves’. Mr Jeuken consents to the inclusion in the
report of the matters based on his information in the form and context in which it appears.
Parkway Minerals confirms that it is not aware of any new information or data that materially
affects the information included in the original market announcement dated 5 November 2020.
Parkway Minerals confirms that the form and context in which the Competent Person’s
findings are presented have not been materially modified from the original market
announcement.
December 2020
|
QUARTERLY REPORT
| 6
CORPORATE
Funding
During the quarter, the Company experienced increased cash outflows (in line with budget
and guidance), largely as a result of expenditures associated with the KLPP-PFS, and to a
lesser extent, the construction of the aMES® pilot plant. These expenditures have were
finalised during the quarter and will not extend into a subsequent reporting period.
The Company remains well funded with a cash balance of $2.62 million at 31 December 2020.
In addition to the cash balance at quarter end, the Company holds an additional ~$2.4 million
in marketable securities (shares and options in Davenport Resources), and a range of other
non-dilutive funding sources outlined below, ensuring Parkway Minerals is well funded to
execute the CY2021 business plan.
Strategic Placement
During the quarter, the Company successfully conducted a placement to sophisticated and
professional investors, raising gross proceeds of $1,604,280, through the issuance of
178,253,330 new fully paid ordinary shares at an issue price of $0.009. Allotment of the
placement shares was made pursuant to the Company’s ASX Listing Rule 7.1 capacity.
Termination of Acuity Capital Facility
During the quarter, the Company utilised the existing Controlled Placement Agreement (CPA)
with Acuity Capital, to raise an additional $36,000, without issuing additional shares. The
Company subsequently terminated the CPA, without incurring any costs.
Grant Funds
The Company (through AWT & CPC subsidiaries), has historically had a strong track-record
in securing a range of grants to subsidise the costs of performing innovative research and
development (R&D) and associated commercialisation activities. To date, the company has
been successful in all innovation and technology related grant application it has applied for,
including a number of highly competitive and prestigious Australian Research Council (ARC)
grants.
The majority of KLPP-PFS related tasks performed at Victoria University, including the
installation, commissioning and testing of a state-of-the-art aMES® pilot plant, is being funded
by a previously awarded ARC supported grant. Subsequent to quarter-end, the Company
secured additional grant funding, as outlined in the Activities Subsequent to Reporting Period
section, below.
Ongoing R&D related activities involving the iBC ® technology continue to be supported by an
Innovations Connections Grant, awarded in June 2020.
Parkway Minerals acknowledges the financial support of the Australian Government.
R&D Rebate
Given the ongoing research and development activities being performed and/or funded by the
Company, the Company anticipates receiving an Australian Government research and
development tax incentive (R&DTI) payment by way of a refundable tax offset in the order of
$235,000 for FY20. The application was finalised during the quarter, with a refund anticipated
in the March 2021 quarter.
December 2020
|
QUARTERLY REPORT
| 7
Cash on Hand
At 31 December 2020, the company had $2.62 million in cash reserves and approximately
$2.40 million in marketable securities.
Investments
Strategic Investment – Davenport Resources (ASX: DAV)
Parkway Minerals owns 34,267,700 shares in Davenport Resources (ASX: DAV),
representing approximately 15.97% of the issued capital of Davenport Resources (as of the
date of this report). Davenport Resources is an ASX listed junior mining company which has
assembled a portfolio of advanced potash projects in Germany, which collectively represent
one of the largest undeveloped potash resource inventories in Western Europe. Given the
globally significant scale of the potash resource delineated by Davenport Resources in an
existing potash producing region, Parkway Minerals believes there is an opportunity for
Davenport Resources to create and unlock substantial value.
Investor Relations
The Company has recently rejuvenated the Parkway Minerals website to reflect the increased
importance on commercialising a world-class technology portfolio to provide long-term
sustainable solutions for processing complex brines, in the energy, mining and wastewater
industries. Additional details including recent news and interviews with the managing director,
are also available at the Parkway Minerals website.
On 01 Dec 2020, the Company release an updated corporate presentation providing details
of recent achievements, the corporate strategy and how the Company is partnering with
leading industry participants to provide, BPaaS – Brine Processing as a Solution™.
Following the 2020 Annual General Meeting held on 23 December 2020, the managing
director of the Company, Bahay Ozcakmak, provided a corporate update presentation.
IRMA
The Company recently became a member of IRMA, the Initiative for Responsible Mining
Assurance. IRMA has developed a comprehensive global standard for measuring and
reporting on environmental, social and corporate governance (ESG) related factors, with the
standard increasingly being supported and adopted by major mining industry stakeholders.
The Company believes it is important to signal to all stakeholders the intention to not only
uphold, but provide leadership in relation to the ESG standards, particularly in terms of
improved environmental compliance, where the Company’s suite of technologies, can play a
significant role in achieving better outcomes, for all stakeholders.
Other Items
During the quarter, $224,000 was spent on exploration and evaluation (mostly in relation to
the KLPP-PFS), $195,000 in staff costs and $108,000 in administration and related corporate
costs. Additional details are provided in the attached Appendix 5B.
Payments to Related Parties
As outlined in the attached Appendix 5B (section 6.1), during the quarter approximately
$116,000 in payments were made to related parties and their associates for director salaries,
consultancy fees, superannuation and other related costs.
December 2020
|
QUARTERLY REPORT
| 8
Tenement Interests
As at 31 December 2020 Parkway Minerals held the following tenements:
Australian Projects – Karinga Lakes Potash Project
Tenement ID
ELRA/32206
ELRA/32207
ELRA/32208
ELRA/32209
ELRA/32210
ELRA/32211
ELRA/32212
ELA/32249
ELA/32250
ELA/32251
(1)
Location
Karinga Lakes
Karinga Lakes
Karinga Lakes
Karinga Lakes
Karinga Lakes
Karinga Lakes
Karinga Lakes
Karinga Lakes
Karinga Lakes
Karinga Lakes
State
NT
NT
NT
NT
NT
NT
NT
NT
NT
NT
Interest
15% (1)
15% (1)
15% (1)
15% (1)
15% (1)
15% (1)
15% (1)
15% (1)
15% (1)
15% (1)
ELRA indicates an Exploration Licence Retention Area, whereas ELA indicates an Exploration Licence
Application. See note above, under heading Karinga Lakes Potash Project with respect to ongoing
tenement rationalisation process.
Activities Subsequent to Reporting Period
Business Development
The Company has recently acquired a lease over an integrated office and warehouse complex
covering ~1,000m2 in inner Melbourne. The Company is also actively recruiting a number of
experienced personnel to fill key Melbourne based roles, which together with the new office
and warehouse facilities, will support both existing and additional business priorities. Further
details regarding these initiatives are expected to be provided during the March 2021 quarter.
Intellectual Property
On 11 January 2021, the Company was advised by IP Australia that:
•
The trade mark application by Activated Water Technologies Pty Ltd (AWT) to register
aMES as a trade mark, has been successful. On this basis, the Company will now refer
to the underlying technology through the registered trade mark aMES ® (trade mark
number: 2093133).
•
The trade mark application by Parkway Process Technologies Pty Ltd to register iBC
as a trade mark, has been successful. On this basis, the Company will now refer to the
underlying technology through the registered trade mark iBC® (trade mark number:
2093140).
Successfully securing registered trade marks for the Company’s core process technologies,
represents another important step in the IP protection and commercialisation process.
December 2020
|
QUARTERLY REPORT
| 9
Grant Funding
On 13 January 2021, a subsidiary of the Company, AWT secured further funding under the
Australian Research Council Industrial Transformation Hub for Energy-Efficient Separation
(IH170100009). The additional funding consists of:
•
$103,000, from the Australian Research Council (ARC)
•
$75,000, from Victoria University (cash component)
•
$140,472, from Victoria University (in-kind component)
•
$147,576, cash commitment from AWT to unlock above funding.
These grant funds will continue to support the ongoing commercialisation of the aMES®
technology. The Company acknowledges and appreciates the ongoing support of Victoria
University and the Australian Government through the Australian Research Council.
On behalf of Parkway Minerals NL.
Bahay Ozcakmak
Managing Director
The attached Appendix 5B has been authorised for release by Bahay Ozcakmak (MD)
and Robert Van der Laan (CFO).
Additional Information
For further information contact:
Bahay Ozcakmak
Managing Director
T: +61 414 596 007
E: bahay@parkwayminerals.com.au
December 2020
|
QUARTERLY REPORT
| 10
aMES® Technology
The activated Mineral Extraction System, or aMES® is
an innovative process technology that enables the
treatment of concentrated brine solutions to recover a
range of valuable compounds, reagents and fresh
water. The technology utilises a proprietary multistaged process incorporating novel membrane
technology and is based on proprietary IP,
incorporating patents, expertise and know-how
acquired over more than a decade of intense process
development.
Advantages of the aMES® technology include:
•
improvements in mineral recovery and
product quality,
•
opportunity for substantial project capex &
opex savings,
•
efficient use of energy and produces pure
water as a by-product, and
•
improved project footprint and environmental
sustainability.
Ongoing collaboration with a number of brine project
developers and operators has confirmed there are
many applications where the aMES® technology has
the potential to deliver substantial value by enhancing
existing flowsheets, in order to improve overall project
performance.
aMES®
Brine Processing Technology
Key Industries (Applications)
•
Mining natural brine (salt lakes)
•
Solution mining brine (potash)
•
Refinery & industrial waste brine
•
Wastewater treatment brine
Target Products (Produced)
•
Potash (MOP/SOP/KMS)
•
Lithium and magnesium salts
•
Range of byproducts (B, Br, Ca,
Co, Cu, I, Na, Ni, REE, Si, Sr)
•
Reagents
•
Water
Additional Information
www.parkwayminerals.com.au/ames-technology
iBC® Technology
The integrated Brine Causticization, or iBC® is a
patented process technology that simultaneously
removes common impurities from waste brine streams
and converts sodium carbonates and bicarbonates
commonly found in coal seam gas (CSG) brines, into
more soluble sodium hydroxide.
As a result of the causticization step, the iBC®
technology produces a purified brine suitable for
downstream processing, including with the aMES®
technology, for the production of various salt products
and industrial-grade sodium hydroxide.
iBC®
Brine Pre-Treatment Technology
Key Industries (Applications)
•
Oil & gas waste brine (CSG)
•
Wastewater treatment brine
Target Products (Produced)
•
Sodium hydroxide concentrate
Additional Information
•
Sodium chloride
https://www.parkwayminerals.com.au/ibc-technology
•
Byproducts (Ca, Mg, Si)
December 2020
|
QUARTERLY REPORT
| 11
About Parkway Minerals
In October 2019, Parkway Minerals (ASX: PWN) completed a transformational transaction by acquiring
an Australian unlisted public company, Consolidated Potash Corporation (CPC). Through CPC,
Parkway Minerals acquired a minority interest in the Karinga Lakes Potash Project (KLPP) in NT
Australia, as well as a majority interest in the New Mexico Lithium Project (NMLP), in the United States.
The CPC transaction, also resulted in Parkway Minerals acquiring the innovative aMES® technology,
which has been developed to process a range of challenging brine streams from the mining industry,
in order to recover valuable minerals, reagents as well as produce fresh water.
Given the significant market opportunities, Parkway Minerals is focused on commercialising a worldclass technology portfolio to provide long-term sustainable solutions for processing complex brines, in
the energy, mining and wastewater industries. In order to achieve this objective, Parkway Minerals is
partnering with leading industry participants to provide, BPaaS – Brine Processing as a Solution™.
Strategic Investment
Parkway Minerals holds a strategic investment in Davenport Resources (ASX: DAV), which has
successfully delineated a globally significant in-situ potash resource (in excess of 550 million tonnes of
contained potash), at its South Harz project in Central Germany. Recently completed scoping studies
have delivered excellent technical and economic results and provide Davenport Resources with an
attractive opportunity to create and unlock substantial value.
Parkway Minerals is commercialising a world-class technology portfolio to provide long-term
sustainable solutions for processing complex brines, in the energy, mining and wastewater
industries.
Our mission is to collaborate with leading strategic partners to deliver:
BPaaS – Brine Processing as a Solution™.
Forward-Looking Statements
This ASX Release may contain certain “forward-looking statements” which may be based on forward-looking information that are
subject to a number of known and unknown risks, uncertainties, and other factors that may cause actual results to differ materially
from those presented here. Where the Company expresses or implies an expectation or belief as to future events or results, such
expectation or belief is expressed in good faith and believed to have a reasonable basis. Forward-looking information includes
exchange rates; proposed or projected project or transaction timelines; uncertainties and risks associated with the advantages
and/or performance of the Company’s projects and/or technologies; uncertainties and risks regarding the estimated capital and
operating costs; uncertainties and risks regarding any envisaged timelines in relations to any results, milestones, partnerships,
including but not limited to any milestones which may require obtaining approvals from third parties.
For a more detailed discussion of such risks and other factors, see the Company’s oth
Share your feedback