QUEENSLAND BRINE SOLUTIONS (QBS) RELEASES:
MASTER PLAN PRESENTATION
Highlights
§
Master Plan presentation provides details on improving the sustainability of the CSG industry.
§
Roadmap for addressing waste brine and salt challenges and creating substantial value.
§
Technology underpinning Master Plan has opportunity to become best available technology.
§
Master Plan is consistent with government priorities, including Australia’s new Critical Minerals
Strategy, which outlines sovereign capability & sustainable supply chains as key objectives.
Parkway Corporate Limited (“Parkway” or the “Company”) (ASX: PWN) is pleased to provide an
introductory presentation outlining the Master Plan being advanced by Queensland Brine Solutions
(QBS), a wholly owned subsidiary of Parkway. Further details regarding Master Plan, are outlined below
and in the attached presentation.
What is Master Plan?
The coal seam gas (CSG) industry in Queensland is expected to produce in the order 6,000,000 tonnes
of waste salts, over the life of existing CSG project. In order to address these significant CSG derived
waste brine and salt challenges, Parkway has recently developed Master Plan, an innovative,
sustainability driven concept.
For context, the transport, dewatering (concentration), crystallisation and encapsulation (disposal) of
the 6 million tonnes of waste salts through the CSG industry’s proposed base case option (salt
encapsulation facilities), is estimated by Parkway to cost in the excess of $20 billion over the life of
operating projects.
What is the Objective of Master Plan?
The primary objective of Master Plan is to utilise a proprietary process technology package developed
by Parkway, to convert all the CSG derived waste brine and salts produced in Queensland, into saleable
industrial products. This approach will put the CSG industry on a more sustainable footing, by
addressing community concerns, by providing a sustainable waste “disposal” (convert waste-toproducts) option along circular economy principles, as well as generating revenue from the sale of
industrial chemical products. A key product produced through the Master Plan concept, is caustic soda,
a key reagent in the production of alumina, as well as in the refining process of various critical minerals.
What is Best Available Technology (BAT)?
At present, despite over $100M being invested by the CSG Industry in Queensland over the last decade,
no sustainable option has been identified to address this significant waste brine and salt challenges.
Subject to successful commercial-scale project execution, Parkway’s proprietary process technology
package has a realistic opportunity of becoming the best available technology (BAT) and provide a
complete industry-wide solution through QBS. Parkway’s technology package been demonstrated to
eliminate waste in-line with circular economy principles, and is expected to achieve significantly
improved project economics, than the proposed salt encapsulation approach.
Based on preliminary internal estimates by Parkway, as outlined in the attached presentation, in
addition to the many sustainability related advantages, the technology-based approach proposed by
Parkway, is expected to create in excess of $15 billion in value for the CSG industry in Queensland. As
the owner of the proprietary process technology package, Parkway (through QBS) is well placed to
capture a share of this substantial value creation, through a range of established industrial technology
related business models.
Who is Queensland Brine Solutions (QBS)?
QBS was recently incorporated by Parkway, in order to pursue the objectives of the Master Plan
concept. Parkway intends to continue to collaborate with a range of stakeholders, including strategic
partners, to assist QBS in the commercialisation of Master Plan.
How will QBS Pursue Master Plan?
QBS, in collaboration with leading strategic partners intends to establish a series of proposed central
waste brine processing hubs. This approach will progressively provide an industry wide solution to
addressing the waste brine and salt challenges facing the Queensland CSG industry, based on BAT.
Master Plan Presentation
The attached Master Plan presentation introduces the Master Plan concept being pursued by QBS,
providing background information, details about the technology-based solution and the commercial
opportunity.
www.
pwnps.com
22 JUNE 2023
|
ASX ANNOUNCEMENT
|
2
COMMENTS FROM GROUP MANAGING DIRECTOR & CEO
Parkway’s Group Managing Director & CEO, Bahay Ozcakmak, makes the following comments:
“
“The development of our Master Plan, for dealing with CSG derived waste brine and salt
disposal related challenges across the entire Queensland CSG industry, is an ambitious
undertaking. Whilst our concept for Master Plan will invariably evolve as we continue to engage
with industry, government and a range of other key stakeholders, our underlying commitment
to utilising world-class technology, to solve complex wastewater related challenges,
sustainably, will remain unchanged.
Our Master Plan provides a high-level roadmap for solving a nationally significant
environmental challenge, impacting billions of dollars of investment, and aligns with many key
government priorities supporting circular economy principles involving the conversion of
industrial wastes into products.
In recent years, we have methodically assembled an impressive portfolio of proprietary brine
processing technologies and capabilities, specifically focused on large-scale industrial
opportunities, including the Australian CSG sector. In addition to our highly experienced
engineering team and accomplished board, we are also fortunate to have long established
strategic partnerships with both Victoria University and Worley, which have been critical to our
ongoing success. Following several years of intense process development, we are now at a
stage where our commercialisation activities have progressed sufficiently, for us to disclose
further details about our Master Plan.
With the support of our partners, we have systematically developed an industrial-grade end-toend brine processing solution specifically developed for the Queensland CSG industry. Our
proprietary technology platform has undergone extensive technical and commercial
evaluations and is now ready to play a key role in addressing the multibillion-dollar challenges
facing the CSG industry. We look forward to working closely and collaboratively with both
industry and government to ensure we achieve improved outcomes for all stakeholders.”
The release of this announcement has been approved by Parkway’s Group Managing Director & CEO,
Bahay Ozcakmak, on behalf of the board of directors of the Company.
ADDITIONAL INFORMATION
For further information or investor enquiries, please contact:
Bahay Ozcakmak
General Enquiries
Group Managing Director & CEO
1300 7275929
solutions@pwnps.com
1300 PARKWAY
www.
pwnps.com
22 JUNE 2023
|
ASX ANNOUNCEMENT
|
3
PARKWAY INVESTOR HUB
To stay up to date with the latest news, access additional investor related resources including research
reports and interact with Parkway by posting questions and feedback through a Q&A function, we
encourage investors to sign-up to the Parkway Investor Hub.
How to sign-up to the Parkway Investor Hub
1. navigate to https://investorhub.pwnps.com/welcome
2. follow the prompts to sign up for an Investor Hub account.
3. complete your account profile.
or Scan QR Code to visit the Parkway Investor Hub.
ABOUT PARKWAY CORPORATE LIMITED
Parkway Corporate Limited is an Australian cleantech company focused on developing and
implementing, industrial-scale innovative water treatment solutions. Parkway is listed on the
Australian Securities Exchange (ASX: PWN) and is emerging as an innovative player in water related
sustainability solutions. With significant inhouse technical expertise and established partnerships,
Parkway is well-placed to deliver the next generation of wastewater treatment plants, incorporating
the company’s portfolio of world-class technologies.
Parkway operates through three (3) core business units, comprising:
•
Parkway Process Solutions (PPS) – Parkway’s primary operating division and an emerging
provider of industrial water treatment products, services, solutions and associated technology
to customers throughout Australia. PPS has recently established commercial relationships with
key water industry participants, including globally recognised OEMs;
•
Parkway Process Technologies (PPT) – Parkway’s technology development, acquisition, and
commercialisation division. PPT owns a portfolio of industrial wastewater treatment
technologies, including the patented aMES® and iBC® process technologies. PPT has global
aspirations and is supported by a network of strategic partners, including global engineering
company Worley; and
•
Parkway Ventures (PV) – holds a portfolio of project equity interests, including interests relating
to Parkway’s Karinga Lakes Potash Project in the Northern Territory of Australia.
Additional information regarding Parkway, including an overview of the corporate structure of Parkway
and the companies in its corporate group, can be found at: www.pwnps.com
FORWARD-LOOKING STATEMENTS
This announcement may contain certain “forward-looking statements”. The words “continue”, “expect”,
“forecast”, “potential” and other similar expressions are intended to identify “forward-looking
statements”. Indications of (and any guidance on) future earnings, financial position, capex
requirements and performance are also “forward-looking statements”, as are statements regarding
internal management estimates and assessments of market outlook.
Where Parkway expresses or implies an expectation or belief as to future events or results, such
expectation or belief is expressed in good faith and believed to have a reasonable basis. However,
“forward-looking statements” are not guarantees of future performance and involve known and unknown
risks, uncertainties and other factors, many of which are beyond the control of Parkway, its officers,
employees, agents and advisors, that may cause actual results to differ materially from those expressed
or implied in such statements. There can be no assurance that actual outcomes will not differ materially
from these statements. There are usually differences between forecast and actual results, because
events and actual circumstances frequently do not occur as forecast and their differences may be
material.
Parkway does not undertake any obligation to publicly release any revisions to any "forward-looking
statements" to reflect events or circumstances after the date of this announcement, or to reflect the
occurrence of unanticipated events, except as may be required under the applicable securities laws.
www.
pwnps.com
22 JUNE 2023
|
ASX ANNOUNCEMENT
|
4
MASTER PLAN
CONCEPT
22 June 2023
Bahay Ozcakmak
ASX: PWN | pwnps.com
Group Managing Director & CEO
Disclaimer
Forward-Looking Statements
Completeness and Accuracy of Information
This presentation may contain forward-looking statements. The
words “continue”, “expect”, “forecast”, “potential” and other
similar expressions are intended to identify forward-looking
statements. Indications of, and guidance on, future earnings,
financial position, capex requirements and performance are also
forward-looking statements, as are statements regarding
internal management estimates and assessments of market
outlook.
No representation or warranty is made as to the accuracy, completeness or correctness
of the information contained in this presentation. To the maximum extent permitted by
law, none of Parkway, its directors, employees or agents or any other person, accept any
liability for any loss arising from or in connection with this presentation including (without
limitation) any liability arising from fault or negligence, or make any representations or
warranties regarding, and take no responsibility for, any part of this publication and make
no representation or warranty, express or implied, as to the currency, accuracy, reliability,
or completeness of information in this announcement.
Where the Company expresses or implies an expectation or
belief as to future events or results, such expectation or belief is
expressed in good faith and believed to have a reasonable basis.
However, forward-looking statements are not guarantees of
future performance and involve known and unknown risks,
uncertainties and other factors, many of which are beyond the
control of Parkway, its officers, employees, agents and advisors,
that may cause actual results to differ materially from those
expressed or implied in such statements. There can be no
assurance that actual outcomes will not differ materially from
these statements. There are usually differences between
forecast and actual results, because events and actual
circumstances frequently do not occur as forecast and their
differences may be material.
The Company does not undertake any obligation to release
publicly any revisions to any "forward-looking statements" to
reflect events or circumstances after the date of this
presentation, or to reflect the occurrence of unanticipated
events, except as may be required under the applicable
securities laws.
No Professional Advice
The information in this presentation does not take into account individual investment and
financial circumstances and is not intended in any way to influence a person dealing with
any securities in Parkway. This presentation does not include any financial, legal or
taxation advice. Any person intending to deal in Parkway securities is recommended to
obtain professional advice.
Additional Information
This presentation has been prepared by Parkway Corporate Limited (“Parkway” or the
“Company”)(ASX: PWN) and has been released on the ASX announcement platform and is
also available at the Company website:
www.pwnps.com
Additional information regarding the Company can also be found at the Company’s
website, or by contacting the Company at:
ir@pwnps.com
Image on presentation cover, is of brine ponds associated with Shell QGC Orana Water Treatment Plant.
Parkway Corporate Limited (ASX:PWN) | Queensland Brine Solutions (QBS) | MASTER PLAN – Concept | 22 June 2023
www.
pwnps.com
|
2
Contents
Outline
Key Definitions
1.
Introduction to QLD CSG-LNG Sector
page 4
2.
The Waste Brine & Salt Challenge
page 9
3.
The QBS Technology-Based Solution
page 21
4.
QBS Master Plan – Overview
page 31
5.
QBS Master Plan – Value Creation
page 36
Appendices
§ Parkway – About Us
page 47
§ Parkway – An Experienced Team
page 48
§ Parkway – Group Structure
page 49
§ Parkway – Key Markets
page 50
§ Parkway – Next-Generation Solutions
page 51
§ Multilayered IP Protection Strategy
page 52
§ Additional Information
page 53
APPEA
Australian Petroleum Producers & Exploration Association
BAT
Best Available Technology
CAPEX
Capital Expenditure
CSG
Coal Seam Gas
DER
Department of Resources (Queensland Government)
DES
Department of Environment & Science (Queensland Government)
DRDMW Department of Regional Development, Manufacturing & Water (Queensland Government)
EPCM
Engineering, Procurement, Construction & Management
FCF
Free Cashflow
FEED
Front-End Engineering Design
FID
Final Investment Decision
GAB
Great Artesian Basin
IP
Intellectual Property
LNG
Liquified Natural Gas
OEM
Original Equipment Manufacturer
OPEX
Operating Expenditure
QBS
Queensland Brine Solutions
RO
Reverse Osmosis (water treatment plant)
RWF
Regulated Waste Facility
SEF
Salt Encapsulation Facility
WTP
Water Treatment Plant
Key Units
$
Australian Dollars, unless stated otherwise
MLD
Megalitres Per Day
MTPA
Million Tonnes Per Annum
TPA
Tonnes Per Annum
Parkway Corporate Limited (ASX:PWN) | Queensland Brine Solutions (QBS) | MASTER PLAN – Concept | 22 June 2023
www.
pwnps.com
|
3
1: Introduction to QLD CSG-LNG Sector
Overview
Presentation Outline
§ Queensland Coal Seam Gas (CSG) Industry
§ Section 1: Introduction to QLD CSG-LNG Sector
§ Overview of Queensland CSG-LNG Projects
§ Section 2: The Waste Brine & Salt Challenge
§ CSG Water Production
§ Section 3: The QBS Technology-Based Solution
§ QLD CSG-LNG Industry and Parkway Timeline
§ Section 4: QBS Master Plan – Overview
§ Section 5: QBS Master Plan – Value Creation
Appendices
§ Parkway – About Us
§ Parkway – An Experienced Team
§ Parkway – Group Structure
§ Parkway – Key Markets
§ Parkway – Next-Generation Solutions
§ Parkway – Multilayered IP Protection Strategy
§ Additional Information
Parkway Corporate Limited (ASX:PWN) | Queensland Brine Solutions (QBS) | MASTER PLAN – Concept | 22 June 2023
www.
pwnps.com
|
4
Queensland Coal Seam Gas (CSG) Industry
Gas Resources
§ The majority of coal seam gas (CSG) resources and
reserves in Queensland, are hosted within the:
§ Bowen Basin, and
§ Surat Basin.
Investment Profile
§ During the early 2010’s, >$80 billion invested in building
25 Mtpa in liquefied natural gas (LNG) export capacity:
§ APLNG, 9 Mtpa (Origin led)
§ GLNG, 7.8 Mtpa (Santos led)
§ QCLNG, 8.5 Mtpa (Shell led)
Production Profile
§ In 2022, the three LNG projects in Gladstone exported
24.3 Mt of LNG, ~6% of global LNG production:
§ Majority of gas exported to Asia, generating
estimated >$25 billion in export revenue in 2022.
Regulatory Profile
Geoscience Australia, Gas: Australia’s Remaining Gas Reserves, period ending June 2021.
§ Projects are governed by a robust regulatory framework.
Parkway Corporate Limited (ASX:PWN) | Queensland Brine Solutions (QBS) | MASTER PLAN – Concept | 22 June 2023
www.
pwnps.com
|
5
Overview of Queensland CSG-LNG Projects
UPSTREAM
GAS OPERATIONS
§
Globally significant
upstream CSG operations
§
Upstream CSG operations,
supply gas to 3 downstream
LNG plants in Gladstone,
Queensland
JOINT VENTURE PARTNERS
&/OR SHAREHOLDERS
GLNG
PROJECT
APLNG
PROJECT
Downstream
Gas Operations
SHELL QGC
PROJECT
ARROW
PROJECT
Upstream
Gas Operations
Parkway Corporate Limited (ASX:PWN) | Queensland Brine Solutions (QBS) | MASTER PLAN – Concept | 22 June 2023
www.
pwnps.com
|
6
CSG Water Production
Where does the gas and water come from?
§ CSG is an unconventional gas resource found in coal deposits.
§ The production of gas requires the dewatering (removal of groundwater
from) the coal seams, to allow the gas to flow to surface.
Complex CSG water requires treatment
§ The CSG water contains a wide range of impurities, including:
§ Dissolved salts (sodium chloride/bicarbonate/carbonate)
§ Other inorganic compounds (including heavy metals & halogens)
§ Range of organic compounds (including suspended solids)
§ Residual hydrocarbon related and other complex impurities
Production of salt products
§ Treatment of CSG water produces waste brine containing impurities
§ The sustainable processing of CSG water involves exploring options for
utilising waste brine and avoiding its ultimate disposal in the form of
mixed salts, into landfill.
No viable long-term solution
Queensland Government, Coal Seam Gas Brine Management Action Plan 2023-33.
§ Despite significant investment by industry, no viable long-term solution
to processing waste brine sustainably, has been identified.
Parkway Corporate Limited (ASX:PWN) | Queensland Brine Solutions (QBS) | MASTER PLAN – Concept | 22 June 2023
www.
pwnps.com
|
7
QLD CSG-LNG Industry and Parkway Timeline
CSG Industry Milestones
Construction of QCLNG
commences, world first
project to convert CSG
into LNG
1996
Parkway Related Milestones
Parkway Minerals lists on
the Australian Securities
Exchange (ASX:PWN)
2011
2012
Queensland Government
released the: Coal Seam
Gas Brine Management
Action Plan 2023-2033
University of Queensland
published Independent
Review of the 2018
APPEA Report
CSG Water Management
Policy released – outlining
saline waste
management priorities
2010
R&D activities relating to
hypersaline brines,
including CSG at Victoria
University and CPC-AWT
APPEA released landmark
report: Queensland gas:
end-to-end water use,
supply and management
First CSG derived LNG
cargo exported from
Gladstone in Queensland
Commencement of
domestic CSG production
in Queensland
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
Acquired the patented
iBC® technology and
associated IP
Acquired Activated Water
Technologies (CPC)
including aMES® brine
processing technology
Signed Global Strategic
Partnership Agreement
with global engineering
company - Worley
Extensive process
simulation, development,
optimisation and piloting
of iBC® technology
Acquired comprehensive
brine technology portfolio
from Victoria University &
broadened partnership
Successful validation of
several major technical
breakthroughs
Commissioned large
capacity innovative pilot
plant incorporating iBC®
and related technologies
Parkway Corporate Limited (ASX:PWN) | Queensland Brine Solutions (QBS) | MASTER PLAN – Concept | 22 June 2023
Disclosure of Master Plan
Concept and related
technology innovations
Completion of
comprehensive feasibility
study for a major CSG
Operator
www.
pwnps.com
|
8
2: The Waste Brine & Salt Challenge
Overview
Presentation Outline
§ CSG Brine & Salt Challenges in Queensland
§ Section 1: Introduction to QLD CSG-LNG Sector
§ Existing Desalination Plants Produce Waste Brine
§ Section 2: The Waste Brine & Salt Challenge
§ Waste Brine Contains Significant Waste Salts
§ Section 3: The QBS Technology-Based Solution
§ The Scale of the Waste Salt Problem
§ Section 4: QBS Master Plan – Overview
§ Shell QGC – Existing State-of-the-Art Technology
§ Section 5: QBS Master Plan – Value Creation
§ CSG Regulatory Framework in Queensland
§ CSG Policy Framework in Queensland
Appendices
§ Long-Term Brine & Salt Management Options
§ Parkway – About Us
§ Community Concerns & Scepticism
§ Parkway – An Experienced Team
§ Parkway – Group Structure
§ Parkway – Key Markets
§ Parkway – Next-Generation Solutions
§ Parkway – Multilayered IP Protection Strategy
§ Additional Information
Parkway Corporate Limited (ASX:PWN) | Queensland Brine Solutions (QBS) | MASTER PLAN – Concept | 22 June 2023
www.
pwnps.com
|
9
CSG Brine & Salt Challenges in Queensland
Overview
§ Production of CSG, results in large volumes of brine production, all of which are currently stored in brine ponds on an “interim” basis.
§ Industry, through APPEA, has explored range of options, over many years, resulting in only 1 viable option, namely “salt encapsulation”.
§ Salt encapsulation is expensive, complex, represents unacceptable environmental risks and faces significant community backlash.
1
3
2
Adapted from: APPEA, QUEENSLAND GAS: end-to-end water use, supply and management, 2018.
1.
Water Treatment Plants
§ x16 large capacity water treatment plants in operation
2.
Regulated Brine Ponds
§ x36 large brine ponds, storing waste CSG derived brines
3.
Proposed Industry Solution (Base Case), involves:
§ Transporting brine to a brine concentrator and salt crystalliser
§ Crystallisation of waste salts that then need to be transported
§ Waste salts to be disposed in a regulated waste facility (RWF)
§ Fees payable to RWF operator as well as government levies
Parkway Corporate Limited (ASX:PWN) | Queensland Brine Solutions (QBS) | MASTER PLAN – Concept | 22 June 2023
www.
pwnps.com
| 10
Existing Desalination Plants Produce Waste Brine
Reject brine (9%)
Formation Water
Produced
annually
50 GL of fresh water recovered annually
Fresh water (91%)
§
55 GL of CSG formation (brackish) water produced annually
§
4.8 GL
Desalination Process
16 major desalination
plants treat brackish
water to produce:
9% recovered
as brine
§
Network of large reverse
osmosis (RO) desalination
plants treat brackish (salty)
CSG formation water:
§
resulting in large volumes of
waste brine production
91% of brackish
water recovered
as fresh water
Fresh Water
For local
agriculture
Existing Desalination Plants
Reject Brine
Produced by
desal process
Parkway Corporate Limited (ASX:PWN) | Queensland Brine Solutions (QBS) | MASTER PLAN – Concept | 22 June 2023
www.
pwnps.com
| 11
Waste Brine Contains Significant Waste Salts
The industry plans to transport
concentrated brine from
existing desalination plants;
to centralised hubs, for:
§ brine concentration, and
§ salt crystallisation.
Reject Brine
Produced by
desal process
§
Waste brine contains
~194,000 tonnes of waste
salt, annually.
§
~6,000,000 tonnes will be
produced over life of
existing CSG projects.
Planned Brine
Concentrators
Energy Intensive
750 ML
BRINE TREAMENT PLANS
Based on existing Base-Case
4.8GL (4,800 ML) of Reject Brine produced by desalination process annually
ANNUAL WASTE PROFILE
Based on existing Base-Case
Planned Salt
Crystallisers
Produce mixed
waste salts
Concentrate
Planned waste
brine profile
Existing Desalination Plants
Waste Salt
Salt requiring
disposal
Parkway Corporate Limited (ASX:PWN) | Queensland Brine Solutions (QBS) | MASTER PLAN – Concept | 22 June 2023
www.
pwnps.com
| 12
The Scale of the Waste Salt Problem
6 million tonnes
tonnes of waste salts dissolved in water (brine),
over the life of 4 major existing CSG projects.
The 4 major CSG projects in Queensland store
brine in 36 ponds with large proportion of salts
already produced.
The Great Pyramid of Giza, was the tallest manmade structure in the world for 3,800 years.
The 2.3 million blocks which make up the Giant
Pyramid of Giza, weigh an estimated
6 million tonnes.
Waste brine ponds associated with Shell QGC Orana Water Treatment Plant.
Parkway Corporate Limited (ASX:PWN) | Queensland Brine Solutions (QBS) | MASTER PLAN – Concept | 22 June 2023
www.
pwnps.com
| 13
Legacy of Potash Mining in Germany
“Monte Kali”, a mountain of residual waste salts from historical potash mining, overlooking the town of Heringen in Hesse, Germany.
Parkway Corporate Limited (ASX:PWN) | Queensland Brine Solutions (QBS) | MASTER PLAN – Concept | 22 June 2023
www.
pwnps.com
| 14
Shell QGC – Existing State-of-the-Art Technology
Overview
§ During 2011-13, QGC (BG, now Shell)
invested ~$1 billion to build two largescale brine concentration plants.
§ The brine concentration plants, take the
reject brine from the desalination (RO)
plants, and concentrate this brine
approximately 7x, thereby reducing the
waste brine volumes significantly.
Operations
§ The brine concentration plants are
operated and maintained by Veolia under
an $800 million, 20-year service contract,
which commenced in 2013.
Outcome
§ Despite the significant CAPEX and OPEX,
the brine concentration plants only
concentrate the salts in brine, but do not
produce any clean or mixed salts (for
sale or disposal, respectively), as the
installation of salt crystallisers are
required to enable salt production.
Shell QGC, 100 MLD Northern Water Treatment Plant built by Consortium of GE and Laing O’Rourke. Image courtesy of GE.
Parkway Corporate Limited (ASX:PWN) | Queensland Brine Solutions (QBS) | MASTER PLAN – Concept | 22 June 2023
www.
pwnps.com
| 15
CSG Regulatory Framework in Queensland
Overview
§ The regulatory framework applicable to CSG projects in Queensland is primarily determined by Queensland Government legislation
governing the industry, requiring compliance with certain performance and environmental standards. In addition, CSG projects are
also impacted by Commonwealth Government legislation, including the EPBC Act 1999.
Queensland Government
The Queensland Government has a rigorous framework in place for the regulation of resource and prescribed activities. This regulatory
framework is comprised by a range of legislation and associated regulations, policies, and guidance materials which impose a number
of requirements and restrictions on an operator when undertaking an activity.
§ The Environment Protection Act 1994
§ Coal Seam Gas Water Management Policy 2012
§ Includes the prioritisation hierarchy for managing saline waste
§ State Development and Public Works Organisation Act 1971
§ Planning Act 2016
§ Waste Reduction and Recycling Act 2011
§ Includes the waste levy framework
§ Regional Planning Interests Act 2014
WASTE MANAGEMENT HIERARCHY
ACTION
Prevention
OUTCOME
Best
Re-use
Recycle
Recovery
Disposal
Worst
Commonwealth Government
§ The Commonwealth Government also regulates CSG activities through the “water trigger” in the Environment Protection and
Biodiversity Conservation Act 1999 (EPBC Act 1999). Under the water trigger, large CSG developments that are likely to have a
significant impact on a water resource are a matter of national environmental significance, requiring Commonwealth approval.
Parkway Corporate Limited (ASX:PWN) | Queensland Brine Solutions (QBS) | MASTER PLAN – Concept | 22 June 2023
www.
pwnps.com
| 16
CSG Policy Framework in Queensland
Key Principles of CSG Brine Management
§ In March 2023, the Queensland Government released the Coal Seam Gas Brine Management Action Plan 2023-2033.
§ The plan reiterated (from Coal Seam Gas Water Management Policy 2012) the prioritisation hierarchy for managing saline waste is:
§ Priority 1 Brine or salt residues are treated to create useable products wherever feasible.
§ Priority 2 After assessing the feasibility of treating the brine or solid salt residues to create useable and saleable products,
disposing of the brine and salt residues in accordance with strict standards that protect the environment.
§ The Action Plan indicated that, “Management of brine requires the consideration of a range of elements including water management,
waste management, water quality, site characteristics, environmental impacts, economic consideration, and safety. To achieve the best
outcomes for the environment, industry and the community regarding the management of brine, the
Share your feedback
Discover