Quarterly Activities/Appendix 5B Cash Flow Report
Released
Released
Announcement PDF
ASX Announcement
29 April 2026
MARCH 2026 – QUARTERLY REPORT
HIGHLIGHTS
Operations
§ Strong quarterly operating performance and on track for record full year (FY26) result.
§ Execution of major water infrastructure project well underway following successful ramp-up.
§ Onboarded operations manager to drive further improvements in operational performance.
Technology
§ Advancing key activities for QBS Brine Management Complex (QBMC) project development.
§ Progressing through key DA related milestones, with public notification currently underway.
§ Partnering with major global OEM/EPC partners to develop brine processing product range.
Corporate
§ Discussions with strategic partners to support project development and corporate growth.
§ The director/chairman search process formally commenced, led by external search firm.
§ Quarterly investor webinar scheduled for 11:00am AEST on Wednesday 29 April 2026.
Testing Underway
to Expand QBMC
Brine Options
Assessment of additional
sources of non-CSG brine.
Record Quarterly
Operating Revenue
of $5.21 million
Bolstered by major water
infrastructure project.
Group Profitability
Underpinned by
$0.73 million EBITDA
Growth in project revenue
underpinning earnings.
Ramped-Up Major
Construction
Project
Execution of major project
ramped-up to capacity.
Developing Brine
Processing Modular
Product Range
OEM/EPC partnering for
innovative product range.
Key Development
Application (DA) for
QBMC Progressing
Advancing rapidly, public
notification underway.
www.pwnps.com MARCH 2026 | QUARTERLY REPORT | 2
MELBOURNE, Australia – Parkway Corporate Limited (“Parkway” or the “Company”) (ASX: PWN,
FSE: 4IP) is pleased to report its activities for the quarter ending 31 March 2026.
Introduction
Parkway is a leading Australian water & wastewater treatment and process technology company
primarily operating through two strategically integrated divisions:
§ Industrial Operations
§ Industrial Technology
As the Industrial Operations division continues to grow, it is increasingly providing Parkway with an
inhouse project delivery platform to support the commercialisation of a portfolio of proprietary process
technologies, being developed by the Industrial Technology division.
INDUSTRIAL OPERATIONS
Parkway’s Industrial Operations are performed through Parkway Process Solutions (PPS) and are
predominantly focused on the provision of conventional water and wastewater treatment related
products and specialty project execution related services. In addition, PPS collaborates closely with
leading industrial companies including with energy, mining and major engineering contractors as well
as municipal water authorities, to provide a range of water infrastructure related engineered solutions.
Operating Performance
During the reporting period, PPS generated operating revenues of $5.21 million, underpinned by a
strong contribution from project execution related activities. The ongoing focus on strategically targeting
projects requiring specialised engineered solutions, continues to support underlying earnings.
Additional details about the financial performance of PPS are provided in the Corporate section.
Business Development & Outlook
PPS continued to experience significant growth by systematically securing new business from a diverse
range of clients, for the provision of industrial water & wastewater treatment related products, services
and solutions. During the period, PPS expanded its accredited vendor status with new major Australian
and international companies, including receiving initial orders from APA Group and Siemens, amongst
others. The expanding PPS client base provides a strong growth platform and supports future project
and revenue generation opportunities as these relationships continue to grow and mature.
As previously disclosed1
, PPS is a key SMP (structural, mechanical & piping) contractor for one of the
largest municipal resource recovery projects currently under construction in Australia (Figure 1). The
key procurement activities for this project by PPS are nearing completion with fabrication related
activities nearing completion. Following initial site-access related delays in late CY25, during the period
the PPS team mobilised to site and successfully ramped up to a peak crew size of 30 FTE towards the
end of the reporting period. The extensive progress at the resource recovery project has made a
significant contribution to the increase in revenue during the period. Subject to further revisions in the
project schedule, the currently awarded works are expected to continue at peak rates on site until the
end of Q1-FY27. As project execution related activities progress, PPS is forecasting a material increase
in revenue recognition underpinning a record FY26 result. This high-profile project continues to highlight
the strategically valuable project delivery capabilities of PPS in supporting major water infrastructure.
In summary, the growth outlook for PPS remains encouraging with record revenue anticipated for FY26
and heading into FY27, as Parkway has a solid project backlog as well as a substantial pipeline of
project opportunities which are expected to underpin future revenue growth and profitability.
1
Refer to 25 June 2025 ASX announcement, available at Parkway Investor Hub: https://pwn.investorhub.com/announcements/7021813
www.pwnps.com MARCH 2026 | QUARTERLY REPORT | 3
Figure 1: Major Resource Recovery Project – Under Construction
Image relates to project status during prior period. Image courtesy of John Holland Group.
INDUSTRIAL TECHNOLOGY
Parkway’s Industrial Technology related activities are performed through Parkway Process
Technologies (PPT) and are predominantly focused on innovative process technology related R&D,
including process development, evaluation, optimisation and piloting, as well as a range of technology
scale-up and commercialisation related activities.
Technology Development
By leveraging the process engineering capabilities of Parkway, PPT continues to build a portfolio of
proprietary technologies, capable of providing highly integrated process solutions, for a range of
complex wastewater and industrial process streams traditionally considered difficult to treat. PPT has
developed innovative applications for these technologies, including applications resulting in
improvements in the processing and treatment of challenging industrial wastewater streams, particularly
for large scale industrial, oil & gas, mining and mineral processing related operations.
www.pwnps.com MARCH 2026 | QUARTERLY REPORT | 4
PPT Priorities
The development and commercialisation of a portfolio of proprietary process technologies remains an
important priority for Parkway, with a range of ongoing activities focused on realising the substantial
advantages of the PPT technology portfolio. Although these technology development related activities
are currently being advanced in the context of coal seam gas (CSG) related solutions for Queensland
Brine Solutions (QBS), these technologies have broader applications, which Parkway is also
concurrently pursuing, particularly given Parkway’s growing project delivery capabilities.
Further details are provided in the Technology Commercialisation – Industrial section, below.
Technology Commercialisation – Queensland Brine Solutions (QBS)
Background
Since the large-scale development of the CSG industry in Queensland in 2010 and the corresponding
establishment and subsequent transition to the export of liquified natural gas (LNG) commencing in
2015, the CSG industry has been a significant part of the Queensland economy contributing an
estimated $127 billion2
to the state economy during the last decade. Notwithstanding the existing scale
of the CSG industry, the Queensland Energy Roadmap 2025 report3
released on 10 October 2025
highlights the important role gas production will continue to play in the Queensland energy sector and
is expected to underpin the continued expansion of the CSG industry in Queensland.
Over the life of currently operating CSG projects in Queensland, an estimated 6 million tonnes of waste
salts are forecast to be produced by these projects. A significant proportion of these salts have already
been produced, in the form of waste brine and are currently being stored in regulated waste brine
storage ponds, awaiting a viable long-term disposal solution. The disposal of waste brine and salts
through salt encapsulation as contemplated by the CSG industry, present extensive environmental risks
and challenges and remains deeply unpopular, with significant opposition from many stakeholders.
Following extensive evaluations and feedback from industry and other stakeholders, in 2023 QBS
developed a roadmap for providing an industry-wide solution to the waste brine and salt related
challenges facing the Queensland CSG industry (refer, QBS Master Plan4
), based on the best available
technology (BAT) being commercialised by Parkway.
Developing an Integrated Solution
Parkway has developed a roadmap for providing an industry-wide solution to the waste brine and salt
related challenges facing the Queensland CSG industry, based on BAT. Parkway intends to lead the
development of strategic brine processing related infrastructure, by leveraging its proprietary
technologies to address significant industry challenges (provision of liquid waste management
services), whilst concurrently creating significant value through the production of industrial chemicals.
An overview of the integrated brine management solution being developed by QBS through the QBMC
project is outlined below, in Figure 2.
QBMC Scope
As outlined in the 2025 AGM Presentation5
, the QBMC is intended to be developed in 4 stages (refer
Figure 4), with each stage processing in the order of 75,000 tonnes of contained salts in CSG derived
brine, annually. At full scale development, the QBMC will have the capacity to process all the existing
and forecast CSG derived salts in Queensland, permanently, providing a transformational industry-wide
solution based on BAT to an intractable issue that has challenged the CSG industry for many years.
2
A Decade of Natural Gas, Australian Energy Producers, available at:
https://energyproducers.au/all_news/a-decade-of-natural-gas-delivers-127-billion-boost-to-qld-economy/
3
Queensland Energy Roadmap 2025, available at: https://www.treasury.qld.gov.au/policies-and-programs/energy/energy-roadmap/.
4
Refer to 22 June 2023 ASX announcement, available at Parkway Investor Hub: https://investorhub.pwnps.com/announcements/4372527.
5
Refer to 26 November 2025 ASX announcement, available at Parkway Investor Hub: https://investorhub.pwnps.com/announcements/7280044
www.pwnps.com MARCH 2026 | QUARTERLY REPORT | 5
Figure 2: Queensland Brine Solutions (QBS) – QBMC Integrated Brine Management Solution
Strategic QBMC Site
On 17 October 2025 Parkway announced6
its wholly owned subsidiary QBS secured a 10-hectare site
(Figure 3) in the heart of the CSG industry in the Western Downs region of Queensland, as the proposed
location to develop the QBMC project. Since successfully securing the QBMC project site, Parkway has
been focused on securing applicable development approvals, partnering with key stakeholders as well
as capability development, to support the accelerated development of the QBMC project.
Figure 3: QBS Brine Management Complex (QBMC) – Regional Context
New oil and gas discoveries in the Taroom Trough (~50km west of QBMC), continue to highlight the
highly strategic location of the QBMC project. The Queensland Government recently established a
whole-of-basin framework, using a new Works Regulation to streamline infrastructure development and
approvals, as part of the Taroom Trough Development Plan7
approved on 23 April 2026.
6
Refer to 17 October 2025 ASX announcement, available at Parkway Investor Hub: https://pwn.investorhub.com/announcements/7213310
7
Refer to Queensland Government media statement, available at: https://statements.qld.gov.au/statements/104942
1
www.pwnps.com |
Parkway Corporate Limited (ASX:PWN) | 2025 AGM - MD PRESENTATION | 26 November 2025
QBMC
QBS Brine
Management
Complex
QBEC
QBS Brine
Electrochemical
Complex
Product 1
Caustic soda (NaOH)
Product 2
Hydrochloric acid (HCl)
Product 3
Other green chemicals
CSG Brine
Transport brine direct to
QBMC for processing
CSG Brine
Pre-concentrated on-site
to reduce brine volume
CSG Brine
Pre-treated on-site to
reduce off-site waste
Other Industrial Brine
Transport brine direct to
QBMC for processing
Water Recovered
During processing at QBMC is available
for agriculture (Crossroads Energy)
Integrated Complex
QBEC will be developed
as an integrated part of
the QBMC project
QBS – Liquid Waste Management Services QBS – Industrial Chemical Complex Logistics Operations
QBMC Nominal Capacity
Capacity to process up to
100% of total CSG industry
waste brines and/or salts
Transport
Product and brine transport
managed by specialised
transport contractors
Flagship project being
developed in stages by QBS
Chemical Products
Existing supply chains
BRINE MANAGEMENT COMPLEX
Orana Gas
Processing
Facility
Kenya Water
Treatment
Hub
High-voltage power
transmission lines, red
Major regional
substation infrastructure
Kogan Condamine Rd
major E-W road, yellow
Kenya Chinchilla
pipeline (scheme water)
Chinchilla Tara Rd
major N-S road, yellow
QBMC to Brisbane
(290km east by road)
QBMC
Upstream
150km+ to
north west
Upstream
~100km to
north west
Upstream
~50km to
north west
Upstream
50 - 100km
to east
QBMC
Brisbane
Gladstone
MAP NOT TO SCALE
All distances are direct, with actual
road routes longer than indicated.
All annotations indicative only, not
to be relied upon for any purpose.
Upstream
35 - 125km+
to north west
Upstream
50 - 100km+
to west
Taroom Trough
Basin Centred
Gas (BCG) play
Key players in emerging TT-BCG play
Upstream
130km+ to
north west
0 km 1 km 2 km 3 km 4 km
www.pwnps.com MARCH 2026 | QUARTERLY REPORT | 6
An overview of the indicative development concept for QBMC is outlined below, in Figure 4.
Figure 4: QBS Brine Management Complex (QBMC) – Indicative Development Concept
QBMC Business Case
Ongoing technoeconomic evaluations performed by QBS in recent years, including during the reporting
period continue to confirm the robust business case for developing the QBMC project. Indicative
financial metrics outlined in the 2025 AGM Presentation8
, highlight the encouraging investment case
for developing the QBMC. Once approved, given the highly strategic nature of the QBMC, QBS will be
well placed to provide a highly differentiated and valuable portfolio of services to industry, based on the
core waste-to-chemicals strategy underpinned by BAT. In several instances, the development,
operation and/or expansion of upstream CSG production is constrained by the inability to safely store
and/or dispose of concentrated brines, highlighting the strategic opportunities for QBS to unlock
substantial value for industry, through the development of the QBMC.
In addition to CSG derived brines, during the period Parkway also evaluated other highly problematic
non-CSG derived waste brines in the region requiring complex processing and/or disposal. Preliminary
findings indicate these non-CSG brines are also suitable for processing at the QBMC project.
The recent Middle East conflict has negatively impacted supply chains for many industrial chemicals,
including key reagents planned to be produced by the QBMC (caustic soda and hydrochloric acid, refer
Figure 2). The reduced supply and increased prices for these essential industrial reagents further
improves the economics of the QBMC project and highlights the importance of domestic supply chains.
QBMC Approvals
The development of the QBMC is subject to a range of conditions precedent including (but not limited
to) relevant approvals, suitable commercial arrangements, funding and a final investment decision.
On 22 December 2025, QBS submitted a Development Application (DA) for stages 0 and 1 of the
proposed QBMC to the relevant assessment authority, the Western Downs Regional Council (WDRC).
On 16 January 2026, QBS received notice from WDRC that the DA (inclusive of Environmental
Authority, EA) was properly made, thereby progressing the application from the Application Stage to
the Information and Referral Stage. As outlined in the Activities Subsequent to Reporting Period section,
Parkway recently finalised a comprehensive response to the information request and progressed to the
public notification stage (refer Figure 5) of the approvals process.
Based on the encouraging progress to date, Parkway remains optimistic DA approval will be secured
in coming months, paving the way for the staged development of the QBMC project.
8
Refer to 26 November 2025 ASX announcement, available at Parkway Investor Hub: https://investorhub.pwnps.com/announcements/7280044
1
www.pwnps.com |
Parkway Corporate Limited (ASX:PWN) | 2025 AGM - MD PRESENTATION | 26 November 2025
Project Profile
§ Overview: Strategic waste-to-chemicals project.
§ Ownership: 100% QBS, pre-equity sell-down.
§ Status: Approvals & feasibility study underway.
Indicative Financials*
§ NPV >$2 billion at full-scale development.
§ Strong forecast returns (IRR >30%).
§ Phased (stages 1-4) development approach.
Proponent
QBMC Preliminary Layout
It should be noted this preliminary layout is intended for illustrative purposes only and will change materially
as the project configuration is optimised based on feedback from a range of stakeholders.
Development of the planned PV solar and battery energy storage system (BESS) do not form part of the
QBMC and are being pursued by Crossroads Energy as part of the broader Crossroads Sustainability Precinct.
power grid
Financial metrics are preliminary in nature and will be updated as part of planned feasibility study, therefore should not be relied upon for any purpose. Refer to slide 34 for further details.
www.pwnps.com MARCH 2026 | QUARTERLY REPORT | 7
Figure 5: QBS Brine Management Complex (QBMC) – DA Public Notification Signage (Sign 1 of 2)
Technology Commercialisation – Industrial
In parallel with the R&D activities relating to the portfolio of innovative process technologies and
commercialisation activities being advanced by QBS, Parkway is also progressing the
commercialisation of PPT’s additional proprietary flowsheets, with applications in industrial, mining and
other major industries.
Modular Packaged Systems
Parkway is leveraging its core process technology capabilities to develop a core product range focused
on complex brine, i) pre-treatment, ii) concentration, iii) crystallisation and iv) chemical synthesis. These
modular product packages will support the rapid development of the QBMC project, as well as provide
an efficient go-to-market capability to offer these packaged systems to third parties. Given Parkway’s
recognised expertise in brine processing technologies, Parkway frequently receives inbound interest
from external parties seeking to procure suitable process equipment like the modular packaged systems
under development. Parkway is collaborating with multiple leading global equipment (OEM) and
engineering (EPC) contractors, to develop this state-of-the-art offering based on pre-qualified systems,
with further details including strategic partnership agreements to be disclosed in the near term.
Unlike typically commoditised water treatment equipment such as ultrafiltration (UF) and seawater
reverse osmosis (SWRO) systems offered by industrial water treatment providers including PPS, PPT
is focused on delivering more complex and differentiated solutions, providing a more defensible and
therefore higher margin offering.
CORPORATE
Financial Summary
Parkway generated record group operating revenues of approximately $5.21 million during the reporting
period, a 45% increase from the prior corresponding period ($3.59m, Q3-FY25).
A summary of key financial metrics during the last 15 months, is outlined below in Figure 6.
www.pwnps.com MARCH 2026 | QUARTERLY REPORT | 8
Figure 6: Group Financial Summary (Q3-FY25 – Q3-FY26)
Note: All financial metrics for the reporting period are based on management accounts and have not been audited, therefore are subject to revision. It should
be noted that EBITDA is a non-GAAP measure. Parkway calculates this excluding non-recurring and non-operational items such as profit or loss on sale of
assets, impairments, redundancies and share-based compensation.
Revenue Outlook
Given the encouraging outlook outlined in the Business Development & Outlook section above, the
growth in operating revenues is expected to continue to accelerate strongly heading into the next
quarter (Q4-FY26).
EBITDA
As outlined in Figure 6, the record quarterly operating revenue of $5.21 million, underpinned strong
underlying earnings resulting in $0.73 million in EBITDA for the period.
Cash Flow
Cash receipts from customers were $4.07 million during the quarter. During the same period, Parkway
consumed $0.07 million in operating cash flow, whilst $0.57 million was consumed by investing activities
(inclusive of capitalised R&D) and $0.13 million for financing activities. Standard security retentions for
the major infrastructure project ($0.4 million increase during period) are materially complete and
scheduled to be released on applicable practical completion (PC) and conclusion of defect liability
period (DLP). Without the security retention related deduction operating cash flow would be $0.30
million. Further details on group cash flow are outlined in items 1.9, 2.6 and 3.10 of the attached
Appendix 5B, respectively. As of 31 March 2026, the company held $1.70 million in cash reserves.
R&D Expenditure
As a technology focused company, Parkway continues to invest in a range of commercially oriented,
industrial research and development related initiatives through the Industrial Technology division. As a
result of these ongoing activities, Parkway is eligible for certain, Australian Government research and
development tax incentive (R&DTI) related reimbursements. Preliminary estimates indicate Parkway is
likely to receive a similar R&DTI reimbursement to the prior year ($0.90 million in FY25) for FY26.
Inventory
The supply of specialised industrial water treatment related products continues to be an important
-$1.0
$0.0
$1.0
$2.0
$3.0
$4.0
$5.0
$6.0
Q3 FY25 Q4 FY25 Q1 FY26 Q2 FY26 Q3 FY26
Millions
EBITDA Operating Revenue Operating Cash Flow
www.pwnps.com MARCH 2026 | QUARTERLY REPORT | 9
component of Parkway’s go-to-market strategy for the Industrial Operations division operated by PPS.
On this basis, PPS carries significant product inventory (stock on hand) across its various operations
across Melbourne and in Darwin, with the value of inventory across the group at the end of the period
of $1.48 million. Notwithstanding the ongoing growth of PPS, given recent investments in various digital
initiatives, inventory levels across the group are expected to continue to remain relatively stable.
Other Items
Investor Relations
Based on unsolicited inbound interest from potential strategic partners and investors, during the period
Parkway hosted several tours of key Parkway company and project sites.
The quarterly investor webinar is scheduled for 11:00am AEST on Wednesday 29 April 2026. Further
details are outlined in the Activities Subsequent to Reporting Period section, below.
Board Changes
Following the retirement of former Chairman Mr Stephen van der Sluys on 12 January 2026, Parkway
recently commenced a formal director search process led by an external board search firm to identify
high-calibre candidates capable of supporting the next stage of transformational growth of the company.
Payments to Related Parties
As outlined in the attached Appendix 5B (item 6.1), during the quarter $0.18 million in payments were
made to related parties and their associates for director and key management personnel salaries,
consultancy fees, superannuation, and other related costs.
Activities Subsequent to Reporting Period
QBMC Development Application
The QBMC Development Application (DA) continued to progress through the approvals process. On 16
April, Parkway provided detailed responses to information requests, incorporating specialist consultant
reports including (but not limited to), air quality and bushfire management plan reports, specific to the
planned QBMC project development.
On 24 April 2026, in accordance with the Planning Act 2016, the public notification period for the QBMC-
DA commenced, with submissions closing on 18 May 2026.
Quarterly Investor Webinar
Parkway will be livestreaming the Q3-FY26 quarterly investor webinar.
Details of the Q3-FY26 quarterly investor webinar with short Q&A are as follows:
Date: 11:00am AEST on Wednesday 29 April 2026.
Presenters: Bahay Ozcakmak (Group MD & CEO)
Mike Hodgkinson (Group CFO & Co-Company Secretary)
Register: To register, visit:
https://investorhub.pwnps.com/webinars/XyM4ZP-q3-fy2026-investor-webinar-
parkway-corporate-asx-pwn
Webinar registration will require registration at the Parkway Investor Hub platform
www.pwnps.com MARCH 2026 | QUARTERLY REPORT | 10
On behalf of Parkway Corporate Limited.
Bahay Ozcakmak
Group Managing Director & CEO
The attached Appendix 5B has been authorised for release by Bahay Ozcakmak (Group MD &
CEO) and Mike Hodgkinson (Group CFO and Joint Company Secretary).
ADDITIONAL INFORMATION
For further information or investor enquiries, please contact:
Bahay Ozcakmak General Enquiries
Group Managing Director & CEO 1300 7275929
solutions@pwnps.com 1300 PARKWAY
www.pwnps.com MARCH 2026 | QUARTERLY REPORT | 11
PARKWAY INVESTOR HUB
To stay up to date with the latest news, access additional investor related resources including research reports and
interact with Parkway by posting questions and feedback through a Q&A function, we encourage investors to sign-
up to the Parkway Investor Hub.
How to sign-up to the Parkway Investor Hub
1. navigate to https://investorhub.pwnps.com/welcome
2. follow the prompts to sign up for an Investor Hub account.
3. complete your account profile.
or Scan QR Code to visit the Parkway Investor Hub.
ABOUT PARKWAY CORPORATE LIMITED
Parkway is a leading Australian water & wastewater treatment and process technology company. Parkway is
focused on the commercialisation of a portfolio of innovative process technologies in key industrial markets, as
Parkway believes this is an important and effective strategy for addressing various global water related
sustainability challenges.
In recent years, Parkway has made significant investments in groundbreaking research and development (R&D)
related activities, including in the acquisition, development, validation and optimisation of a comprehensive portfolio
of cutting-edge industrial water treatment related process technologies.
In support of Parkway’s accelerated technology commercialisation strategy, Parkway primarily operates through
two strategically integrated capacities:
§ Industrial Operations business division is focused on the provision of conventional water and
wastewater treatment related products & services, including fabrication as well as project delivery related
services including installation, for a broad range of predominantly commercial, municipal and industrial
clients.
§ Industrial Technology business division is primarily focused on innovative process technology related
R&D, including process screening, evaluation, optimisation and piloting, as well as a range of technology
commercialisation related activities.
Integrated Capabilities
Parkway has assembled a fully integrated inhouse project delivery capability, including for the innovative process
technologies being developed and commercialised by Parkway.
Additional information regarding Parkway, including an overview of the corporate structure of Parkway and the
companies in its corporate group, can be found at: www.pwnps.com
FORWARD-LOOKING STATEMENTS
This announcement may contain certain “forward-looking statements”. The words “continue”, “expect”, “forecast”,
“potential” and other similar expressions are intended to identify “forward-looking statements”. Indications of (and
any guidance on) future earnings, financial position, capex requirements and performance are also “forward-
looking statements”, as are statements regarding internal management estimates and assessments of market
outlook.
Where Parkway expresses or implies an expectation or belief as to future events or results, such expectation or
belief is expressed in good faith and believed to have a reasonable basis. However, “forward-looking statements”
are not guarantees of future performance and involve known and unknown risks, uncertainties and other factors,
many of which are beyond the control of Parkway, its officers, employees, agents and advisors, that may cause
actual results to differ materially from those expressed or implied in such statements. There can be no assurance
that actual outcomes will not differ materially from these statements. There are usually differences between forecast
and actual results, because events and actual circumstances frequently do not occur as forecast and their
differences may be material.
Parkway does not undertake any obligation to publicly release any revisions to any "forward-looking statements"
to reflect events or circumstances after the date of this announcement, or to reflect the occurrence of unanticipated
events, except as may be required under the applicable securities laws.
Rule 5.5
ASX Listing Rules Appendix 5B (17/07/20) Page 1
+ See chapter 19 of the ASX Listing Rules for defined terms.
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
Parkway Corporate Limited
ABN Quarter ended (“current quarter”)
62 147 346 334 31 March 2026
Consolidated statement of cash flows Current quarter
$A’000
Year to date
$A’000
1. Ca