Quarterly Activities/Appendix 5B Cash Flow Report
Released
Released
Announcement PDF
ASX Announcement
30 July 2026
JUNE 2026 – QUARTERLY REPORT
HIGHLIGHTS
Operations
§ Delivery of SMP scope for major water infrastructure project driving record revenue growth.
§ Strong quarterly operating performance underpins record full year result (FY26, unaudited).
§ Successful performance of core project delivery capabilities provides confidence for QBMC.
Technology
§ Advancing key project development activities for QBS Brine Management Complex (QBMC).
§ Secured Environmental Authority (EA) and other key approvals whilst DA approval is advanced.
§ Announced strategic collaboration with Hitachi to develop brine concentration product range.
Corporate
§ Strong cash balance of $2.89 million at end of reporting period.
§ Discussions with strategic partners to support project development and corporate growth.
§ Quarterly investor webinar scheduled for 11:00am AEST on Thursday 30 July 2026.
Ongoing Testing to
Expand QBMC Feed
Brine Options
Evaluation of additional
sources of non-CSG brine.
Record Quarterly
Operating Revenue
of $7.25 million
Bolstered by major
infrastructure project.
Group Profitability
Underpinned by
$0.54 million EBITDA
Growth in project revenue
underpinning earnings.
Delivering SMP for
Major Construction
Project
Structural, mechanical,
piping for major project.
Developing Brine
Concentration
Product Range
Announced strategic
collaboration with Hitachi.
Key Development
Application (DA) for
QBMC Progressing
Secured EA, with DA at
advanced decision stage.
www.pwnps.com JUNE 2026 | QUARTERLY REPORT | 2
MELBOURNE, Australia – Parkway Corporate Limited (“Parkway” or the “Company”) (ASX: PWN,
FSE: 4IP) is pleased to report its activities for the quarter ending 30 June 2026.
Introduction
Parkway is a leading Australian water & wastewater treatment and process technology company
primarily operating through two strategically integrated divisions:
§ Industrial Operations
§ Process Technologies
In addition to providing specialised solutions for industry, Parkway’s Industrial Operations division also
provides an inhouse project delivery platform to support the commercialisation of a portfolio of
proprietary technologies being developed by Parkway’s Process Technologies division.
INDUSTRIAL OPERATIONS
Parkway’s Industrial Operations are performed through Parkway Process Solutions (PPS) and
predominantly focused on the provision of conventional water and wastewater treatment related
products and specialty project execution related services. In addition, PPS also provides leading
industrial companies including energy, mining and major engineering contractors as well as municipal
water authorities, with a range of specialised water infrastructure related engineered solutions.
Integrated Project Delivery Capabilities
PPS leverages core capabilities across the entire project lifecycle, from early process development,
through to equipment selection, fabrication, installation and ultimately commissioning, to deliver
successful project outcomes. Additional details about the core capabilities, integrated solutions and an
extensive list of project references are outlined in the latest PPS Capability Statement1
.
Operating Performance
Parkway’s sustained focus on targeting and prioritising complex high-value infrastructure projects
requiring specialised engineering solutions whilst expanding inhouse capabilities, continues to support
ongoing strategic growth.
As previously disclosed2
, PPS is the key SMP (structural, mechanical & piping) contractor for one of
the largest municipal resource recovery projects currently under construction in Australia (refer page
21 of PPS Capability Statement). This high-profile project showcases the strategically valuable project
delivery capabilities of PPS in delivering complex wastewater treatment related infrastructure.
In addition to demonstrating core capabilities, the ongoing delivery of the PPS scope for this major
infrastructure project has made a significant contribution towards increased operating revenue of $7.25
million generated during the period, underpinning a record full year result (FY26, unaudited). Additional
details about the financial performance of PPS are provided in the Corporate section.
Business Development & Outlook
PPS continues to experience significant growth by systematically securing new business from diverse
clients, for the provision of industrial water & wastewater treatment related products, services and
solutions. During the period, PPS expanded its accredited vendor status with new major Australian and
international companies, which continues to provide a strong growth platform.
1
PPS Capability Statement, available at: https://pwnps.com/collections/pps-capability-statement
2
Refer to 25 June 2025 ASX announcement, available at Parkway Investor Hub: https://pwn.investorhub.com/announcements/7021813
www.pwnps.com JUNE 2026 | QUARTERLY REPORT | 3
PROCESS TECHNOLOGIES
Parkway’s Process Technologies related activities are performed through Parkway Process
Technologies (PPT) and predominantly focused on innovative process technology related R&D,
process development, evaluation, optimisation and piloting, as well as a range of technology scale-up
and commercialisation related activities.
Technology Development
Through PPT, Parkway continues to build a portfolio of proprietary technologies, capable of providing
highly integrated process solutions, for a range of complex wastewater and industrial process streams
traditionally considered difficult to treat. PPT has developed innovative applications for these
technologies, including in the processing and treatment of challenging industrial wastewater streams,
particularly for large scale industrial, oil & gas, mining and mineral processing related operations.
PPT Priorities
The development and commercialisation of a portfolio of proprietary process technologies remains an
important priority for Parkway, with a range of ongoing activities focused on realising the substantial
advantages of the PPT technology portfolio. Although these technology development related activities
are currently being advanced in the context of coal seam gas (CSG) related applications for Queensland
Brine Solutions (QBS), these technologies have broader applications, which Parkway is also
concurrently pursuing, particularly given Parkway’s growing project delivery capabilities through PPS.
Further details are provided in the Technology Commercialisation – Industrial section, below.
Technology Commercialisation – Queensland Brine Solutions (QBS)
Background
Since the large-scale development of the CSG industry in Queensland in 2010 and the corresponding
establishment and subsequent transition to the export of liquified natural gas (LNG) commencing in
2015, the CSG industry has been a significant part of the Queensland economy contributing an
estimated $127 billion3
to the state economy during the last decade. Notwithstanding the existing scale
of the CSG industry, the Queensland Energy Roadmap 2025 report4
highlights the important role gas
production will continue to play in the Queensland energy sector and is expected to underpin the
continued expansion of the CSG industry in Queensland.
Over the life of currently operating CSG projects in Queensland, an estimated 6 million tonnes of waste
salts are forecast to be produced by these projects. A significant proportion of these salts have already
been produced, in the form of waste brine and are currently being stored in regulated waste brine
storage ponds, awaiting a viable long-term disposal solution. The disposal of waste brine and salts
through salt encapsulation as contemplated by the CSG industry, present extensive environmental risks
and challenges and remains deeply unpopular, with significant opposition from many stakeholders.
Following extensive evaluations and feedback from industry and other stakeholders, in 2023 QBS
developed a roadmap for providing an industry-wide solution to the waste brine and salt related
challenges facing the Queensland CSG industry (refer, QBS Master Plan5
), based on the best available
technology (BAT) being commercialised by Parkway.
Recent CSIRO Analysis
On 26 June 2026, CSIRO’s Gas Industry Social and Environmental Research Alliance (GISERA)
3
A Decade of Natural Gas, Australian Energy Producers, available at:
https://energyproducers.au/all_news/a-decade-of-natural-gas-delivers-127-billion-boost-to-qld-economy/
4
Queensland Energy Roadmap 2025, available at: https://www.treasury.qld.gov.au/policies-and-programs/energy/energy-roadmap/.
5
Refer to 22 June 2023 ASX announcement, available at Parkway Investor Hub: https://investorhub.pwnps.com/announcements/4372527.
www.pwnps.com JUNE 2026 | QUARTERLY REPORT | 4
published a landmark report titled, Beneficial reuse and disposal options for brine from the Surat and
Bowen basins – a multicriteria analysis6
. In Parkway’s assessment, the GISERA report provides strong
independent validation of the strategic rationale underpinning the planned QBMC. The GISERA report
concluded that conventional brine disposal options contemplated by industry are becoming increasingly
constrained by environmental, regulatory, technical and social factors, while policy settings continue to
shift towards resource recovery, beneficial reuse and circular economy outcomes.
The GISERA report also identified technical challenges facing industry, that closely align with the
objectives of QBMC and the capabilities of Parkway's proprietary process technologies. Importantly,
one of the most prospective processing pathways highlighted by the report, was the “recovery
(production)” of caustic soda based on a causticisation process. It should be noted the causticisation
process cited in the report is the integrated Brine Causticisation (iBC®
) process, a patented technology
owned by Parkway. Many of the broader challenges associated with the beneficial processing of brine
outlined in the report, including variable brine chemistry and recovered product quality, amongst other
considerations, have already been addressed and form core components of the planned QBMC.
Regulatory Framework Report
QBS recently commissioned a report to investigate the policy and regulatory frameworks that apply to
the production, storage and disposal of CSG derived brines in Queensland. Recent policy and
legislative changes continue to further reinforce the critical role the QBMC will play in addressing a
nationally significant long term waste challenge. Key developments during the period, include
announcement of the Queensland Waste Strategy7
and amendments to the Regional Planning Interests
(Condamine Alluvium) Act8
, both of which further strengthen the importance of developing the QBMC.
The planned release of the Regulatory Framework Report is expected to align with the planned DA
approval date for the QBMC.
Developing an Integrated Solution
Parkway has developed a roadmap for providing an industry-wide solution to the waste brine and salt
related challenges facing the Queensland CSG industry, based on BAT. Parkway intends to lead the
development of strategic brine processing related infrastructure, by leveraging its proprietary
technologies to address significant industry challenges (provision of liquid waste management
services), whilst concurrently creating significant value through the production of industrial chemicals.
An overview of the integrated brine management solution being developed by QBS through the QBMC
project is outlined in Figure 1.
Figure 1: Queensland Brine Solutions (QBS) – QBMC Integrated Brine Management Solution
6
Refer to GISERA report available at CSIRO website: https://gisera.csiro.au/research/surface-and-groundwater/beneficial-reuse-and-disposal-options-for-
brine-from-the-surat-and-bowen-basins-queensland/
7
Queensland Wast Strategy, https://www.qld.gov.au/__data/assets/pdf_file/0036/668169/queensland-waste-strategy-2025-35.pdf
8
Regional Planning Interests, https://www.planning.qld.gov.au/planning-framework/legislation/regional-planning-interests-condamine-alluvium-and-other-
legislation-amendment-act-2026
www.pwnps.com JUNE 2026 | QUARTERLY REPORT | 5
QBMC Scope & Roadmap
Whilst the primary long-term focus of the QBMC is to process CSG derived brines, as outlined in Figure
1, the QBMC development configuration will also enable the processing of other industrial and municipal
waste brines. In addition to the extensive testwork already performed in relation to a range of CSG
derived brines, in recent months Parkway has also been actively testing and evaluating other
problematic waste brines available in the general proximity of the planned QBMC. The strategy of
ensuring QBMC can process a diverse range of brines, provides Parkway with maximum operational
flexibility as well as broader partnering options to pursue the most optimal development roadmap.
As outlined in the 2025 AGM Presentation9
, the QBMC is intended to be developed in 4 industrial-scale
stages (refer Figure 2), with each stage processing approximately 75,000 tonnes of contained salts in
brine, annually. Based on long-established policy and regulatory frameworks, Parkway considers the
current status-quo of storing vast volumes of concentrated CSG derived brines in “temporary” holding
ponds for periods that in many instances have extended beyond a decade to no longer be acceptable.
These challenges have been outlined in the GISERA report and will also be profiled in the Regulatory
Framework Report, to highlight the significant and growing challenges facing the CSG industry. Against
this backdrop, at full scale development, the QBMC will have the capacity to process all the existing
and forecast CSG derived salts in Queensland, permanently, providing a transformational industry-wide
solution to an intractable issue that has challenged the industry for many years.
To accelerate the path-to-market, Parkway is at the advanced stages of planning a Commercial
Demonstration Project (CDP, Stage 0) for the QBMC. In addition to processing a wide range of waste
brines and generating early revenues, the QBMC-CDP is intended to provide engineering data to
underpin a final investment decision (FID) for full-scale development of Stage 1. Given the current
approvals process covers both Stages 0 & 1, upon successful operation of QBMC-CDP, development
of Stage 1 is expected to proceed shortly thereafter and be supported by existing site infrastructure.
Figure 2: QBS Brine Management Complex (QBMC) – Indicative Development Concept
Strategic QBMC Site
On 17 October 2025 Parkway announced10
QBS secured a 10-hectare site (Figure 3) in the heart of
the CSG industry in the Western Downs region of Queensland, as the proposed location to develop the
QBMC project. Since successfully securing the QBMC project site, Parkway has been focused on
securing applicable development approvals, partnering with key stakeholders as well as capability
development, to support the accelerated development of the QBMC project.
9
Refer to 26 November 2025 ASX announcement, available at Parkway Investor Hub: https://investorhub.pwnps.com/announcements/7280044
10
Refer to 17 October 2025 ASX announcement, available at Parkway Investor Hub: https://pwn.investorhub.com/announcements/7213310
www.pwnps.com JUNE 2026 | QUARTERLY REPORT | 6
Figure 3: QBS Brine Management Complex (QBMC) – Regional Context
Recent oil and gas discoveries in the Taroom Trough located approximately 50km west of QBMC,
continue to highlight the highly strategic location of the QBMC project. The Queensland Government
has established a whole-of-basin framework, using a new Works Regulation to streamline infrastructure
development and approvals, as part of the Taroom Trough Development Plan11
approved on 23 April
2026. Although the development of the oil and gas projects in the Taroom Trough is still at a relatively
early stage, with discovered hydrocarbon resources requiring extensive appraisal and evaluation, any
potential development, may provide opportunities for the QBMC to provide specialised liquid waste
management related services.
QBMC Drivers & Business Case
Ongoing technoeconomic evaluations performed by QBS in recent years, including during the reporting
period continue to confirm the robust business case for developing the QBMC project. Indicative
financial metrics outlined in the 2025 AGM Presentation, highlight the encouraging investment case for
developing the QBMC. Once approved, given the highly strategic nature of the QBMC, QBS will be well
placed to provide a highly differentiated and valuable portfolio of services to industry, based on the core
waste-to-chemicals strategy underpinned by BAT. In several instances, the development, operation
and/or expansion of upstream CSG production is constrained by the inability to safely store and/or
dispose of concentrated brines, highlighting the strategic opportunities for QBS to unlock substantial
value for industry, through the development of the QBMC. Parkway notes that CSG project developers
and operators are facing increased pressure to better align with the Coal Seam Gas Water Management
Policy 201212
, in particular the requirement to align with Priority 1, by ensuring that “Brine or salt
residues are treated to create useable products wherever feasible”.
In addition to CSG derived brines, during the period Parkway also evaluated other highly problematic
non-CSG derived waste brines in the region requiring complex processing and/or disposal. Preliminary
findings indicate these non-CSG brines are also suitable for processing at the QBMC project.
The recent Middle East conflict has negatively impacted supply chains for many industrial chemicals,
including key reagents planned to be produced by the QBMC (caustic soda and hydrochloric acid, refer
Figure 1). The reduced supply and increased prices for these essential industrial reagents further
improves the economics of the QBMC project and highlights the importance of domestic supply chains.
11
Refer to Queensland Government media statement, available at: https://statements.qld.gov.au/statements/104942
12
Refer to Queensland Government website to access policy at: https://environment.qld.gov.au/management/activities/non-mining/water/csg-water
BRINE MANAGEMENT COMPLEX
Orana Gas
Processing
Facility
Kenya Water
Treatment
Hub
High-voltage power
transmission lines, red
Major regional
substation infrastructure
Kogan Condamine Rd
major E-W road, yellow
Kenya Chinchilla
pipeline (scheme water)
Chinchilla Tara Rd
major N-S road, yellow
QBMC to Brisbane
(290km east by road)
QBMC
Upstream
150km+ to
north west
Upstream
~100km to
north west
Upstream
~50km to
north west
Upstream
50 - 100km
to east
QBMC
Brisbane
Gladstone
MAP NOT TO SCALE
All distances are direct, with actual
road routes longer than indicated.
All annotations indicative only, not
to be relied upon for any purpose.
Upstream
35 - 125km+
to north west
Upstream
50 - 100km+
to west
Taroom Trough
Basin Centred
Gas (BCG) play
Key players in emerging TT-BCG play
Upstream
130km+ to
north west
0 km 1 km 2 km 3 km 4 km
www.pwnps.com JUNE 2026 | QUARTERLY REPORT | 7
QBMC Approvals
The development of all stages including Stage 0 (CDP) of the QBMC is subject to a range of conditions
precedent including (but not limited to) relevant approvals, suitable commercial arrangements, funding
and a final investment decision.
On 22 December 2025, QBS submitted a Development Application (DA) for stages 0 and 1 of the
proposed QBMC to the relevant assessment authority, the Western Downs Regional Council (WDRC).
On 16 June 2026, the Queensland Government State Assessment and Referral Agency (SARA)
advised QBS that the Environmental Authority (EA) and State-Controlled Road Access Permit
associated with the QBMC-DA had both been approved, subject to relevant conditions.
In light of securing these key approvals and based on the encouraging progress to date, Parkway
remains optimistic DA approval will be secured imminently, paving the way for the staged development
of the QBMC project.
As outlined in the Activities Subsequent to Reporting Period section, Parkway has recently been
advised QBMC’s DA will be considered at the WDRC’s next Council Meeting to be held on 20 August
2026.
Technology Commercialisation – Industrial
In parallel with the commercialisation of process technologies being advanced through QBS, PPT is
also progressing the commercialisation of PPT’s additional proprietary flowsheets, with applications in
industrial, mining and other major industries.
Modular Packaged Systems
Parkway is leveraging its core process technology capabilities to develop a core product range focused
on complex brine, i) pre-treatment, ii) concentration, iii) crystallisation and iv) chemical synthesis. These
modular product packages will support the rapid development of the QBMC project, as well as provide
an efficient go-to-market capability to offer these packaged systems to third parties.
Parkway is collaborating with multiple leading global equipment (OEM) and engineering (EPC)
contractors, to develop this state-of-the-art offering based on pre-qualified systems.
Parkway Hitachi – Ultra-High Brine Concentration Systems
During the period Parkway announced13
it had entered a strategic collaboration with Hitachi to develop
state-of-the-art ultra-high brine concentration systems. The initial focus of the collaboration is the
development of standardised modular brine concentration systems (PH-UHBCS), intended to support
the development of the QBMC, as well as supplied into key global markets.
As outlined in Figure 1, the QBMC will involve brine concentration both upstream (client sites) and
onsite at the QBMC. The PH-UHBCS being jointly developed by Parkway and Hitachi are intended to
provide compact, modularised, high-performance and energy-efficient systems to specifically address
these brine concentration requirements. Parkway is in discussions with several parties regarding
potential offsite brine concentration with PH-UHBCS, with the brine concentrate from these projects
ultimately being processed at the QBMC.
13
Refer to 19 May 2026 ASX announcement, available at Parkway Investor Hub: https://investorhub.pwnps.com/announcements/7543378
www.pwnps.com JUNE 2026 | QUARTERLY REPORT | 8
CORPORATE
Financial Summary
Parkway generated record group operating revenues of approximately $7.25 million during the period,
a 72% increase from the prior corresponding period ($4.22 million, Q4-FY25).
A summary of key financial metrics during the last 15 months, is outlined below in Figure 4.
Figure 4: Group Financial Summary (Q4-FY25 – Q4-FY26)
Note: All financial metrics for the reporting period are based on management accounts and have not been audited, therefore are subject to revision. It should
be noted that EBITDA is a non-GAAP measure. Parkway calculates this excluding non-recurring and non-operational items such as profit or loss on sale of
assets, impairments, redundancies and share-based compensation.
The strong financial performance achieved during the period underpins a record full year result (FY26,
unaudited) and continues the strong multi-year growth trajectory as outlined in Figure 5.
Figure 5: Group Financial Summary (FY21 – FY26)
www.pwnps.com JUNE 2026 | QUARTERLY REPORT | 9
Revenue
Notwithstanding strong revenue growth during the period and the encouraging outlook outlined in the
Business Development & Outlook section above, growth in operating revenues is expected to moderate
(from Q2-FY27) as the major infrastructure project approaches completion.
Whilst only contributing a small share of overall group revenue, during the period the growing PPS
Digital business achieved an important milestone, surpassing $1 million in revenue on a trailing twelve
months (TTM) basis, highlighting the strength of Parkway’s diverse operating business portfolio.
EBITDA
As outlined in Figure 4, the record quarterly operating revenue of $7.25 million, underpinned strong
underlying earnings resulting in $0.54 million in EBITDA for the period.
Cash Flow
Cash receipts from customers were $7.42 million during the quarter. During the same period, Parkway
generated $1.60 million in operating cash flow, whilst $0.69 million was consumed by investing activities
(inclusive of capitalised R&D) and $0.28 million for financing activities. Further details on group cash
flow are outlined in items 1.9, 2.6 and 3.10 of the attached Appendix 5B, respectively. As of 30 June
2026, the company held $2.89 million in cash reserves.
R&D Expenditure
As a technology focused company, Parkway continues to invest in a range of commercially oriented,
industrial research and development related initiatives through the Process Technologies division. As
a result of these ongoing activities, Parkway is eligible for certain, Australian Government research and
development tax incentive (R&DTI) related reimbursements. Preliminary estimates indicate Parkway is
likely to receive a similar R&DTI reimbursement to the prior year ($0.90 million in FY25) for FY26.
Inventory
The supply of specialised industrial water treatment related products continues to be an important
component of Parkway’s go-to-market and digital strategy for the Industrial Operations division
operated by PPS. On this basis, PPS carries significant inventory (stock on hand) across its various
operations with the estimated value of inventory at the end of the period of approximately $1.40 million.
Other Items
Investor Relations
The quarterly investor webinar is scheduled for 11:00am AEST on Thursday 30 July 2026. Further
details are outlined in the Activities Subsequent to Reporting Period section, below.
Payments to Related Parties
As outlined in the attached Appendix 5B (item 6.1), during the quarter $0.18 million in payments were
made to related parties and their associates for director and key management personnel salaries,
consultancy fees, superannuation, and other related costs.
www.pwnps.com JUNE 2026 | QUARTERLY REPORT | 10
Activities Subsequent to Reporting Period
QBMC Development Application (DA)
Further to the DA status provided in the QBMC Approvals section, on 22 July 2026, Parkway was
advised that the DA application for QBMC will be considered at WDRC’s next Council Meeting to be
held on 20 August 2026.
Quarterly Investor Webinar
Parkway will be livestreaming the Q4-FY26 quarterly investor webinar.
Details of the Q4-FY26 quarterly investor webinar with short Q&A are as follows:
Date: 11:00am AEST on Thursday 30 July 2026.
Presenters: Bahay Ozcakmak (Group MD & CEO)
Mike Hodgkinson (Group CFO & Co-Company Secretary)
Register: To register (registration will require registration at the Parkway Investor Hub), visit:
https://investorhub.pwnps.com/webinars/yaGn1r-q4-fy2026-investor-webinar-
parkway-corporate-asx-pwn
On behalf of Parkway Corporate Limited.
Bahay Ozcakmak
Group Managing Director & CEO
The attached Appendix 5B has been authorised for release by Bahay Ozcakmak (Group MD &
CEO) and Mike Hodgkinson (Group CFO and Joint Company Secretary).
ADDITIONAL INFORMATION
For further information or investor enquiries, please contact:
Bahay Ozcakmak General Enquiries
Group Managing Director & CEO 1300 7275929
solutions@pwnps.com 1300 PARKWAY
www.pwnps.com JUNE 2026 | QUARTERLY REPORT | 11
PARKWAY INVESTOR HUB
To stay up to date with the latest news, access additional investor related resources including research reports and
interact with Parkway by posting questions and feedback through a Q&A function, we encourage investors to sign-
up to the Parkway Investor Hub.
How to sign-up to the Parkway Investor Hub
1. navigate to https://investorhub.pwnps.com/welcome
2. follow the prompts to sign up for an Investor Hub account.
3. complete your account profile.
or Scan QR Code to visit the Parkway Investor Hub.
ABOUT PARKWAY CORPORATE LIMITED
Parkway is a leading Australian water & wastewater treatment and process technology company. Parkway is
focused on the commercialisation of a portfolio of innovative process technologies in key industrial markets, as
Parkway believes this is an important and effective strategy for addressing various global water related
sustainability challenges.
In recent years, Parkway has made significant investments in groundbreaking research and development (R&D)
related activities, including in the acquisition, development, validation and optimisation of a comprehensive portfolio
of cutting-edge industrial water treatment related process technologies.
In support of Parkway’s accelerated technology commercialisation strategy, Parkway primarily operates through
two strategically integrated capacities:
§ Industrial Operations business division is focused on the provision of conventional water and
wastewater treatment related products & services, including fabrication as well as project delivery related
services including installation, for a broad range of predominantly commercial, municipal and industrial
clients.
§ Process Technologies business division is primarily focused on innovative process technology related
R&D, including process screening, evaluation, optimisation and piloting, as well as a range of technology
commercialisation related activities.
Integrated Capabilities
Parkway has assembled a fully integrated inhouse project delivery capability, including for the innovative process
technologies being developed and commercialised by Parkway.
Additional information regarding Parkway, including an overview of the corporate structure of Parkway and the
companies in its corporate group, can be found at: www.pwnps.com
FORWARD-LOOKING STATEMENTS
This announcement may contain certain “forward-looking statements”. The words “continue”, “expect”, “forecast”,
“potential” and other similar expressions are intended to identify “forward-looking statements”. Indications of (and
any guidance on) future earnings, financial position, capex requirements and performance are also “forward-
l
Share your feedback